Risk Management Analysis in the Implementation of the Mataram Mayor's Office Development Project
Downloads
In the implementation of construction projects, especially the Mataram Mayor's Office project, various risks can lead to cost overruns, delays in completion, and reduced work quality. During construction, contractors face various uncertainties, so risk management is required. This research aims to identify the source of risk, conduct risk assessments, and formulate mitigation efforts. The method used in this study is the Risk Breakdown Structure (RBS) to identify risks and the AS/NZS 4360:2004 standard to determine the level and category of risk. The identification results showed that 44 risk variables were identified in the project. After the assessment, 6 risks were identified as high risk, 30 as medium risk, and 8 as low risk. Risk management strategies are implemented through monitoring and surveillance to strengthen supply chains, manage logistics, and ensure readiness to address uncertainties such as delays and material shortages. In addition, improving work culture, implementing OHS, systematic change management, effective communication, and adaptive weather planning are key to minimizing risks and maintaining the smooth running of projects.
ALSaadi, N., & Norhayatizakuan, N. (2021). The impact of risk management practices on the performance of construction projects. Studies of Applied Economics, 39(4). https://doi.org/10.25115/eea.v39i4.4164
Alshihri, S., Al-Gahtani, K., & Almohsen, A. (2022). Risk factors that lead to time and cost overruns of building projects in Saudi Arabia. Buildings, 12(7), 902.
Alshehhi, H. (2024). The impact of risk management on the performance of construction projects. Proceedings of Social Science and Humanities Research Association (SSHRA). https://doi.org/10.20319/icbellp.207208
Antoniou, F., & Tsioulpa, A. V. (2024). Assessing the delay, cost, and quality risks of claims on construction contract performance. Buildings, 14(2), 333.
Ayuza, F. (2025). Integrated risk management in the life cycle stages of construction projects in Indonesia. Journal of Authentic Research. https://doi.org/10.36312/jar.v4ispecialissue.3335
Bepari, M., Narkhede, B., & Raut, R. (2024). A comparative study of project risk management with risk breakdown structure (RBS): A case of commercial construction in India. International Journal of Construction Management, 24, 673–682. https://doi.org/10.1080/15623599.2022.2124657
Chammout, B., El-Adaway, I. H., Abdul Nabi, M., & Assaad, R. H. (2024). Price escalation in construction projects: Examining national and international contracts. Journal of Construction Engineering and Management, 150(9), 04024109.
Fakhereldin, F. (2024). Construction claims management practices and dispute resolution mechanisms in construction contracts.
Habetemeherit, A., Mengistu, D., Sorsa, F., & Tesfaye, B. (2025). Causes and impacts of public construction projects’ contract terminations. Engineering, Construction and Architectural Management. https://doi.org/10.1108/ECAM-09-2024-1217
Haqi, F. I. (2023). From policies to actions: Mayoral leadership and local government’s impact on urban resilience in Indonesia. Journal of Resilient Economies, 3(2), 62–76.
Ibrahim, A., Sirajo, A., & Ibrahim, A. (2022). The effects of delay and time management in building construction: A review. International Journal of Scientific Advances. https://doi.org/10.51542/ijscia.v3i4.29
Jabbar, A. L., & Khoiry, M. A. (2025). Construction delays and project profitability: A systematic review. Proceedings of the Institution of Civil Engineers – Management, Procurement and Law, 1–18.
Jiang, X., Lu, K., Xia, B., Liu, Y., & Cui, C. (2019). Identifying significant risks and analyzing risk relationships for construction PPP projects in China using the integrated FISM–MICMAC approach. Sustainability, 11. https://doi.org/10.3390/su11195206
Kebede, S. (2022). Assessment of causes and settlement mechanisms of construction disputes in public work contracts: An Ethiopian perspective. Archives of Civil Engineering, 145–168.
Kurniawan, M. A. D., Susanto, S., & Rahmawati, F. (2025). Occupational health and safety risk analysis using AS/NZS 4360:2004 and HIRARC methods in construction projects. Jurnal Konstruksi, 23, 37–45. https://doi.org/10.33364/konstruksi/v.23-2.2552
Nazali, W., Ngudiyono, & Mahendra, M. (2025). Risk management for implementing housing project development in West Lombok Regency. In Springer Nature (pp. 379–387). https://doi.org/10.1007/978-981-96-4694-4_38
Raodah, P. (2023). The public participation and sustainable development perspective on zero waste policy in Mataram City, NTB Province. Unram Law Review, 7(2).
Suryaningrat, L. R., Hasanah, S., Jiwantara, F. A., & Septyanun, N. (2025). Analysis of the implementation of public services in an electronic-based government system (Mataram City study). International Journal of Health, Economics, and Social Sciences (IJHESS), 7(3), 1643–1648.
Sutarna, I. T., Hakim, A., & Hendriadi, H. (2025). Improving governance and inclusion public services in Selaparang District, Mataram City. Journal of Governance and Local Politics (JGLP), 7(2), 245–252.
Yousri, E., Sayed, A., Farag, M., & Abdelalim, A. (2023). Risk identification of building construction projects in Egypt. Buildings, 13(4), 1084. https://doi.org/10.3390/buildings13041084
Zhasmukhambetova, A., Evdorides, H., & Davies, R. (2025). Integrating risk assessment and scheduling in highway construction: A systematic review of techniques, challenges, and hybrid methodologies. Future Transportation. https://doi.org/10.3390/futuretransp5030
Copyright (c) 2026 Anang Aprillah, Ngudiyono Ngudiyono, Made Mahendra

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.