Analysis of The Impact of Resources on Time Performance in an Oncology Hospital Project

Autori

  • Mohammad Syafei Universitas Mercu Buana
  • Budi Susetyo Universitas Mercu Buana

##semicolon##

https://doi.org/10.59188/eduvest.v6i2.52878

##semicolon##

time performance##common.commaListSeparator## equipment##common.commaListSeparator## work methods##common.commaListSeparator## materials##common.commaListSeparator## human resources

Abstrakt

This study analyzes the influence of resource factors on project completion time performance in an oncology hospital construction project, which has high complexity due to specialized facilities such as radiotherapy rooms with radiation shielding requirements. The variables examined include equipment, work methods, materials, human resources, and financial factors. Data analysis employed a quantitative approach using Partial Least Squares–Structural Equation Modeling (PLS-SEM) to examine structural relationships between latent variables. The inner model analysis yielded an R² value of 0.895, indicating that 89.5% of the variation in project time performance can be explained by the five factors. Direct hypothesis testing revealed that equipment is the most dominant variable (path coefficient 0.415; p-value 0.000), followed by work methods (0.258; p-value 0.012), materials (0.231; p-value 0.006), and human resources (0.142; p-value 0.014). Financial factors showed no significant effect (0.037; p-value 0.731). The study concludes that technical and operational factors—particularly equipment, work methods, materials, and human resources—have a greater influence on project delays than financial aspects. Recommended strategies include optimizing equipment management, strengthening efficient work methods, controlling material supply chains, and improving workforce competence and coordination to enhance time efficiency and project completion success.

##submission.citations##

Aris Sujarwo.Prof. Dr. Dr(TS). Ir. H. Wateno. Oetomo.MM., MT., MH., I. (2022). Jurnal Kacapuri Jurnal Keilmuan Teknik Sipil Volume 5 Nomor 1 Edisi Juni 2022. 5, 269–278.

Balqish, C. N., Buraida, B., Buraida, B., Azan, S. A., & Azan, S. A. (2024). Pemerataan Sumber Daya Manusia Pada Proyek Pembangunan Gedung Rawat Inap Rumah Sakit Umum Daerah (RSUD) Kota Sabang. Journal of The Civil Engineering Student, 6(2), 99–105. https://doi.org/10.24815/journalces.v6i2.28993

Cahyaka, H. W., Wibowo, A., Handayani, K. D., Wardhono, A., Wiyono, A., & Santoso, E. H. (2016). TIM EJOURNAL Ketua Penyunting : Penyunting : Mitra bestari : Penyunting Pelaksana : Redaksi : Jurusan Teknik Sipil ( A4 ) FT UNESA Ketintang - Surabaya Website : tekniksipilunesa . org Email : REKATS.

Faizar, I., & Sumarman. (2016). Analisis Manajemen Kostruksi Proyek Rumah Sakit Arjawinangun Kabupaten Cirebon. Jurnal Konstruksi Unswagati Cirebon, V(2), 227–290.

Fitriana, N. C., & Santosa, B. (2020). Analisis Faktor-Faktor Pemilihan Suplier Material pada Jasa Usaha Konstruksi dengan Metode Fuzzy AHP. Jurnal Fondasi, 9(1), 1–11. https://doi.org/10.36055/jft.v9i1.7440

Haq, S., Abadiyah, S., & Dimastoro, P. (2019). Analisa Optimalisasi Waktu Proyek Dengan Metode Crash Program Pada Proyek Rumah Sakit Di Kota Tangerang. Structure (Jurnal Sipil), 1(1), 1. https://doi.org/10.31000/civil.v1i1.6772

Khilbran, M., & Sakti, W. I. (2019). Indentifikasi Faktor Risiko Human Errors Dalam Penerapan Manajemen Sumber Daya Manusia Di Perusahaan Jasa Konstruksi. Jurnal Muara Sains, Teknologi, Kedokteran Dan Ilmu Kesehatan, 3(1), 45. https://doi.org/10.24912/jmstkik.v3i1.2210

Kurniawan, H., & Anggraeni, I. A. A. (2020). Analisis Risiko Rantai Pasok Material Terhadap Keterlambatan Pelaksanaan Proyek Konstruksi. Rekayasa Sipil, 14(1), 43–50. https://doi.org/10.21776/ub.rekayasasipil.2020.014.01.6

Lailan Tawila Berampu. (2021). Analisis Faktor-Faktor Yang Mempengaruhi Efektivitas Waktu Proyek Dan Dampaknya Terhadap Efektivitas Biaya Proyek Konstruksi (Studi Kasus: Pt Pan Pasific Nesia Subang – Jawa Barat. 3.

Mangare, J. B., Sompie, B. F., Tarore, H., Pascasarjana, D., & Sipil, T. (2012). KAJIAN PROPORSIONAL MODEL SUMBER DAYA PADA PROYEK KONSTRUKSI GEDUNG. 2(3).

Moh Nur Soleh. (n.d.). Manajemen Sumber Daya Manusia Proyek Konstruksi. https://www.google.co.id/books/edition/Manajemen_Sumber_Daya_Manusia_Proyek_Kon/k00HEQAAQBAJ?hl=id&gbpv=1&dq=sumber+daya+proyek+konstruksi&pg=PA113&printsec=frontcover

Mohammad Zaenal Arifin, Budi Susetyo, S. (2022). Analisis Motivasi dan Kepemimpinan Terhadap Keberhasilan Proyek Melalui Kompetensi Sumber Daya Manusia di Proyek Gedung Bertingkat Tinggi. Jurnal Syntax Admiration, 3(1), 163–179. https://doi.org/10.46799/jsa.v3i1.373

Oktra, Delfa. dkk. (2019). Vol. 2 No.1 Edisi 1 Oktober 2019 http://jurnal.ensiklopediaku.org Ensiklopedia of Journal. 2(1), 103–108.

Pelaksanaan, D., Planning, D., Ruang, D. I., Bedah, I., Wates, R., & Progo, K. (2022). Gambaran 5m (man, money, method, material dan machine) dalam pelaksanaan discharge planning di ruang rawat inap bedah rsud wates kulon progo.

Putra, P. T., Hasibuan, Moh. S. R., & Syahadat, R. M. (2018). Pembangunan Rumah Sakit Medika Dramaga Dan Dampaknya Terhadap Kualitas Visual. NALARs, 17(1), 39. https://doi.org/10.24853/nalars.17.1.39-50

Rodhi, N. N. (2024). Faktor Yang Mempengaruhi Kinerja Sumber Daya Manusia Pada Pekerjaan Proyek Konstruksi Gedung Bertingkat Di Bojonegoro. 4, 8409–8416.

Setyowati, D. S., Jurusan, D., Sipil, T., Udayana, U., Jurusan, A., Sipil, T., & Udayana, U. (2020). Konstruksi Di Kabupaten Badung Analysis On The Aspects Of Human Resources Toward The Performance On The Construction Project In The Regency Of. 103–109.

Subagia, I. N. (2021). Analisis Kebutuhan Sumber Daya Kegiatan Pada Proyek Pembangunan Gedung Kantor Camat Payangan Gianyar Bali. 1(2), 1–7.

Sudipta, I. (2013). Studi Manajemen Proyek Terhadap Sumber Daya Pada Pelaksanaan Proyek Konstruksi (Studi Kasus : Pembangunan Villa Bali Air). Jurnal Ilmiah Teknik Sipil, 17(1), 73–83.

Tanning, J., Mara, J., & Sopacua, H. A. I. (2022). Analisis Kinerja Sumber Daya Manusia Pada Proyek Trans Studio Mall Makassar. Paulus Civil Engineering Journal, 4(2), 314–320. https://doi.org/10.52722/pcej.v4i2.461

Waktu, D. A. N., Dinas, D. I., Umum, P., Manado, K., & Willar, D. (2015). Analisis Faktor Keterlambatan Penyelesaian Proyek Konstruksi Gedung Terhadap Mutu , Biaya. 5(2), 401–405.

Wirabakti, D. M., Abdullah, R., & Maddeppungeng, A. (2014). Studi Faktor-Faktor Penyebab Keterlambatan Proyek Konstruksi Bangunan Gedung. Jurnal Konstruksia, 6(1), 15–29.

##submission.downloads##

Publikované

2026-02-24