Analysis of Non-Physical Waste Production Variables (Lean Six Sigma) on Project Time Management Through the Mediation of Lean Construction
DOI:
https://doi.org/10.59188/eduvest.v5i12.52560Keywords:
non physic waste production, time control, lean constructionAbstract
Construction projects are entering an era of profitability, aiming to achieve business goals with minimal resources. Yet, prior research shows only 54% complete on time, due to activity variations causing production waste and delays. This study examines non-physical waste production from the Lean Six Sigma concept's influence on project time management via Lean Construction mediation in the PUSRI 3B project. Methods included identifying delay factors from literature and field observations, categorizing them as Lean Six Sigma non-physical waste, and distributing Likert-scale questionnaires to respondents. Data were analyzed using SmartPLS ver. 4 with Structural Equation Modeling (SEM). Results indicate defect and overproduction waste significantly affect Lean Construction implementation but not time management—present in PUSRI 3B yet mitigated by quality control, avoiding delays. Inventory waste significantly impacts both Lean Construction and time management, contributing to delays. Overall, non-physical waste production significantly influences time management through Lean Construction mediation.
References
Agyekum-Mensah, G., & Knight, A. D. (2017). The professionals’ perspective on the causes of project delay in the construction industry. Engineering, Construction and Architectural Management, 24(5), 828–841.
Antoniou, F., & Tsioulpa, A. V. (2024). Assessing the delay, cost, and quality risks of claims on construction contract performance. Buildings, 14(2), 333.
Bhatta, M., Dhital, M. R., & Karmacharya, P. K. (2023). Identifying the causes and effects of Waste due to Non-Value Adding Activities on Road construction projects in Nepal.
Dara, H. M., Adamu, M., Ingle, P. V., Raut, A., & Ibrahim, Y. E. (2025). An MCDM Approach to Lean Tool Implementation for Minimizing Non-Value-Added Activities in the Precast Industry. Infrastructures, 10(3), 55.
Dara, H. M., Raut, A., Adamu, M., Ibrahim, Y. E., & Ingle, P. V. (2024). Reducing non-value added (NVA) activities through lean tools for the precast industry. Heliyon, 10(7).
Fateh, M. A. M., & Sulaiman, N. A. (2021). Preliminary study on awareness of the lean concept from the non-physical waste perspective. Malaysian Construction Research Journal, 14(3), 12–26.
Gbahabo, P., & Samuel, A. O. (2017). Effects of infrastructure project cost overruns and schedule delays in sub-saharan Africa. 11th International Conference on Social Sciences Helsinki, 20–21.
GEBRE, F. (2021). An Assessment of the Causes of schedule delay and cost overrun: The Case of BamaCon Engineering Plc. ST. MARY’S UNIVERSITY.
Igwe, C., Hammad, A., & Nasiri, F. (2022). Influence of lean construction wastes on the transformation-flow-value process of construction. International Journal of Construction Management, 22(13), 2598–2604.
Igwe, C., Nasiri, F., & Hammad, A. (2022). An empirical study on non-physical waste factors in the construction industry. Engineering, Construction and Architectural Management, 29(10), 4088–4106.
Moon, E. (2020). Delays in Global Engineering Procurement and Construction Projects: Main Factors in Project Management.
Nawir, D., Bakri, M. D., & Syarif, I. A. (2023). Central government role in road infrastructure development and economic growth in the form of future study: the case of Indonesia. City, Territory and Architecture, 10(1), 12.
Nikakhtar, A., Hosseini, A. A., Wong, K. Y., & Zavichi, A. (2015). Application of lean construction principles to reduce construction process waste using computer simulation: a case study. International Journal of Services and Operations Management, 20(4), 461–480.
Nugraha, A. T., Prayitno, G., Situmorang, M. E., & Nasution, A. (2020). The Role Of Infrastructure In Economic GroTth And Income Inequality In Indonesia. Economics & Sociology, 13(1), 102–115.
Omotayo, T., Olanipekun, A., Obi, L., & Boateng, P. (2020). A systems thinking approach for incremental reduction of non-physical waste. Built Environment Project and Asset Management, 10(4), 509–528.
Sahlu, A., & Dinku, A. (2021). Construction site wastes (non-physical) categorization in Addis Ababa based on lean concept. Zede Journal, 39(1), 31–43.
Salim, W., & Negara, S. D. (2018). Infrastructure development under the Jokowi administration: Progress, challenges and policies. Journal of Southeast Asian Economies, 35(3), 386–401.
Samarghandi, H., Mousavi, S., Taabayan, P., Mir Hashemi, A., & Willoughby, K. (2016). Studying the Reasons for Delay and Cost Overrun in Construction Projects: The Case of Iran.
Syadullah, M., & Setyawan, D. (2021). The Impact of Infrastructure Spending on Economic Growth: A Case Study of Indonesia. Komunikácie, 23(3).
Taye, M. (2016). Assessment of time and cost overruns in construction projects (case study at defense construction enterprise). St. Mary’s University.
Vänskä, P. (2025). Applying lean to project management: a conceptual model for reducing waste and lead time in project-based business.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Rakhmad Sugih Hartono, Slamet Riyadi, Fausta Ari Barata

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.