Maintenance Costs Optimization Of Light Rail Transit (LRT) Facilities And Infrastructure Based On Life Cycle Cost Analysis (Case Study: South Sumatra LRT)
DOI:
https://doi.org/10.59188/eduvest.v4i11.1508Keywords:
Light Rail Transit, Maintenance Cost, Life Cycle Cost AnalysisAbstract
The construction of the South Sumatra Light Rail Transit (LRT) requires a huge development cost, besides that it has quite a large annual operational and maintenance cost. In order for South Sumatra LRT maintenance costs to run efficiently and effectively, it is necessary to optimize maintenance costs for South Sumatra LRT facilities and infrastructure based on Life Cycle Cost Analysis. Life Cycle Cost is an economic analysis method that refers to all costs associated with development, operating and maintaining a construction project over a certain period of time (Heralova, 2017). The research objectives were to analyze the physical condition of Facilities and Infrastructure South Sumatra LRT, evaluate South Sumatra LRT maintenance strategies and develop maintenance cost scenarios based on Life Cycle Cost. Based on data processing using the combined condition index method, the total value of the South Sumatra LRT infrastructure components reached 5,718. The physical condition of the South Sumatra LRT infrastructure reviewed is on a good scale with minor damage so that the option of preventive or time-based maintenance activities can be used. For the Life Cycle Cost of South Sumatra LRT infrastructure, the value obtained is IDR 2,080,482,508,541,480.
References
Amani, N., M., A. N., & Samat, R. a. (2012). Infrastructure Component Assessment Using the Condition Index System: Literature Review and Discussion. KICEM Journal of Construction Engineering and Project Management. https://doi.org/10.6106/JCEPM.2012.2.1.027
American Public Transit Association, Glossary of Transit Terminology, American Public Transit Association, Washington DC, USA, 1994.
Anggraini, I. A. (2021). Penilaian Kondisi Bendungan dan Optimasi Biaya pemeliharaan Berdasarkan Life Cycle Cost Analysis. Universitas Indonesia.
Arliansyah, J., Kadarsa, E., & Melania, R. (2022). Desain Noise Barrier Light Rail Transit (Lrt)Palembang Untuk Mengurangi Tingkat Kebisingan. Publikasi Penelitian Terapan Dan Kebijakan, 5(2). https://doi.org/10.46774/pptk.v5i2.504.
Boomen, M. V. D., Schoenmaker, R., & Wolfert, A. R. M. (2018). A Life Cycle Costing Approach for Discounting in Age and Interval Replacement Optimisation Models for Civil Infrastructure Assets. Structure and Infrastructure Engineering, 14.
Chang, D.-Y. (1996). Applications of The Extent Analysis Method on Fuzzy AHP. European Journal of Operational Research, 65. https://doi.org/10.1016/0377-2217(95)00300-2.
Corder, Antony. 1996. Teknik Manajemen Pemeliharaan. Jakarta: Erlangga.
D. Bruckmann, A. Bomhauer-Beins, and U. Weidmann, “A qualitative model to evaluate the financial effects of innovations in the rail sector,” Transportation Research Procedia, vol. 10, pp. 564–573, 2015.
Dananjoyo, R. A., Aminullah, A., Nugroho, A. S. B. (2020). Penerapan Metode Life Cycle Cost dalam Perhitungan Evaluasi Ekonomi Jembatan untuk Penentuan Prioritas Penanganan Jembatan.
El-Akruti, K., Zhang, T., Dwight, R. (2016). Developing an Optimum Maintenance Policy by Life Cycle Cost Analysis – a Case Study
Fuller, S., 2010. Life-cycle Cost Analysis (LCCA). Whole Building Design Guide.
Giunta, M., Bressi, S., & D’Angelo, G. (2018). Life cycle cost assessment of bitumen stabilised ballast: A novel maintenance strategy for railway track-bed. Construction and Building Materials, 172, 751–759. doi:10.1016/j.conbuildmat.2018.04.020.
Goh, K. C., Goh, H. H., Chong, H. (2018). Integration Model of Fuzzy AHP and Life-Cycle Cost Analysis for Evaluating Highway Infrastructure Investments.
Heralova, R. S. (2017). Life Cycle Costing as an Important Contribution to Feasibility Study in Construction Projects. Procedia Engineering, 196.
Heralova, R. S. (2014). Life Cycle Cost Optimization Within Decision Making on Alternative Designs of Public Buildings. Procedia Engineering, 85, 454463. https://doi.org/10.1016/j.proeng.2014.10.572
Huang, M., Dong, Q., Ni, F., Wang, L. (2020). LCA and LCCA based multi-objective optimizationof pavement maintenance.
Herdian, Rozi. (2019). Pengembangan Situs Light Rail Transit (LRT) Palembang Berbasis Analytical Customer Relationship Management (CRM). Universitas Sriwijaya. Palembang.
Hudoyo, C. P. (2018). Pengembangan standar WBS Berbasis Risiko Untuk Meningkatkan Perencanaan Estimasi Biaya Pada Proyek Konstruksi Pelabuhan Laut. Universitas Indonesia.
Illankoon, I. M. C. S., Tam, V. W. Y., Le, K. N., & Wang, J. Y. (2018). Life Cycle Costing for Obtaining Concrete Credits in Green Star Rating System in Australia. Journal of Cleaner Production, 172. https://doi.org/10.1016/j.jclepro.2017.11.202
J. Liang and Z. Liu, “Analysis of urban rail transit operation cost control,” International Journal of Business and Social Science, vol. 5, no. 5, pp. 140–142, 2014.
Kementerian PPN/Bappenas. (2015). Draft Final Business Case / Draft Kajian Akhir Prastudi Kelayakan Report Penyiapan Dokumen Transaksi Proyek Kerjasama Pemerintah Swasta Sumatra Selatan Monorail.
Margaretha, T. N. (2023). Evaluasi Kinerja Pelayanan Light Rail Transit di Kota Palembang. Universitas Islam Indonesia.
Marliansyah, J. (2014). Analisis Rencana Life Cycle Cost Gedung Hostel pada Kawasan Rumah Sakit Jimbun Medika Kediri.
Muda, D. (2021). Analisis Pengaruh Keamanan, Kenyamanan, Dan Aksesibilitas Terhadap Minat Masyarakat Pengguna Mrt Jakarta. Forum Studi Transportasi Antar Perguruan Tinggi, 1(2), 4–6.
Pambudi, A. S., & Hidayati, S. (2020). Analisis Perilaku Sosial Pengguna Moda Transportasi Perkotaan: Studi Kasus Mass Rapid Transit (MRT) DKI Jakarta. Bappenas Working Papers, 3(2), 143–156. https://doi.org/10.47266/bwp.v3i2.74.
Pangestu, Y. (2015). Pemilhan Pemasok Bahan Baku Kayu Handle Raket Dengan Menggunakan Metode Fuzzy Analitycal Hierarchy Process. Jurnal Teknik Industri, Vol. 16, No. 1, Februari 2015, pp. 31-42. ISSN 1978-1431 print / ISSN 2527-4112 online
Perwitasari, D., Rahman, H. Z., Petroceany, J. S., Andreas, A. (2017). Optimasi Kerjasama Pemanfaatan Aset Dalam Pembiayaan Operasional dan Pemeliharaan Stasiun Palmerah.
Plebankiewicz, E., Meszek, W., Zima, K., Wieczorek, D. (2019). Probabilistic and Fuzzy Approaches for Estimatingthe Life Cycle Costs of Buildings under Conditionsof Exposure to Risk.
Putri, Dianyta. (2019). Faktor-Faktor Yang Mempengaruhi Minat Masyarakat Dalam Menggunakan Transportasi Light Rail Transit (LRT) di Palembang. Universitas Sriwijaya. Palembang
Rosyad, F., & Yandi, J. (2019). Analisis Persepsi Pengguna Layanan LRT Kota Palembang. Tekno, 16(1), 421–435.
Saaty, T. L. (1993). Pengambilan Keputusan Bagi Para Pemimpin: Proses Hirarki Analitik untuk Pengambilan Keputusan dalam Situasi yang Kompleks. Pustaka Binaan Pressindo.
Setiono, Koosdaryani, Suryoto, & Ulyanisa, N. (2020). Selera Masyarakat dalam Menentukan Perumahan di Kabupaten Sukoharjo dengan Metode Fuzzy AHP. e-Jurnal Matriks Teknik Sipil, 8. https://doi/org/10.20961/mateksi.v8i2.44178
Sitohang, D. T. R. T. (2018). Pengembangan Standar WBS Untuk Meningkatkan Perencanaan Penjadwalan Pada Proyek Konstruksi Pelabuhan Udara Berbasis Risiko.
Spickova, M., & Myskova, R. (2015). Costs Efficiency Evaluation using Life Cycle Costing as Strategic method. Procedia Economics and Finance 34.
Sugiyono. (2013). Metode Penelitian Kuantitatif, Kualitatif, dan R&D. Alfabeta
Sun, Y., Carmichael, D. G. (2017). Uncertainties Related to Financial Variables Within Infrastructure Life Cycle Costing: a Literature Review.
Taufik & Arliandi, M. (2020). Sistem Informasi E-Ticketing Lrt Kota Palembang. Bina Darma Conference on Computer Science. e-ISSN: 2685-2683p-ISSN: 2685-2675.
V. R. Vuchic, Transportation Engineering and Planning, EOLSS Publisher/UNESCO, Oxford, UK, 2009.
Wayangkau, H. G. (2021). Analisis Manajemen Risiko pada Proyek Pembangunan bendungan (Studi Kasus : Bendungan Titab di Bali, Bendungan Jatibarang di Kabupaten Semarang Dan Bendungan Diponegoro di Semarang). Universitas Diponegoro. Semarang.
Wongkar, Y.K., Tjakra, J., Pratasis, P. A. K. (2016). Analisis Life Cycle Cost Pada Pembangunan Gedung (Studi Kasus: Sekolah St. URSULA Kotamobagu).
Y. Zhu and M. Diao, “The impacts of urban mass rapid transit lines on the density and mobility of high-income households: a case study of Singapore,” Transport Policy, vol. 51, pp. 70–80, 2016.
Yahya, I. N. (2011). Pengelolaan Risiko Proyek Pembangunan PLTU 10.000 MW Dalam Rangka Peningkatan Kinerja Biaya. April.
Zhou, Q., Mao, B., Peng, S., Huang, J., Tian, P. (2023). Analysis of the Impacts of Passenger Demand on the Profitability of Different Types of Urban Rail Transit. Promet – Traffic&Transportation. 2023;35(1):71-86. https://doi.org/10.7307/ptt.v35i1.4185 .
Published
Issue
Section
License
Copyright (c) 2024 Atri Ranindita, Ayomi Dita Rarasati
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.