Analysis Of The Earned Value Method on the Road and Bridge Preservation Project in Situbondo-Ketapang-Banyuwangi
DOI:
https://doi.org/10.59188/eduvest.v4i9.3793Keywords:
Earned Value Method, Project Performance, Project CostAbstract
The implementation of the Situbondo – Ketapang – Banyuwangi Road and Bridge Preservation Project experienced changes in the area being worked on, requiring additional design. Issues arose when the overlay asphalt mix work was halted to await test results for Aspal Modiv PG – 70 from the Pusjatan Bandung Road Materials Laboratory, causing a delay in the 40th week by -0.813%. Delays primarily occurred in the AC - WC and AC - BC asphalt work, affecting project performance. A cost and time analysis was necessary to address this issue. The Earned Value Method (EVM) was used to determine the project's duration and cost until initial handover. The study results indicated that the project cost performance with a CPI > 1 was good, but an SPI of 0.983 < 1 indicated delays. The estimated final project cost is Rp 112,439,121,070.91, with an estimated completion time of 453 days, 3 days longer than the planned schedule.
References
Alkas, M. J., Sari, D. P., Haryanto, B., & Ramadanri, N. A. (2023). Pengendalian Biaya Dan Waktu Proyek Dengan Metode Analisis Nilai Hasil Menggunakan Microsoft Project (Vol. 1, Issue 1). Doi.
Arifin, M. F. A., Sarifatuzzuhriyah, M., & Liu, S. S. (2023). Cost And Time Control Analysis With Earned Value Method In The Mrt-Hub Building Construction. Jurnal Teknik Sipil Dan Perencanaan, 25(1), 90–99. Https://Doi.Org/10.15294/Jtsp.V25i1.43043
Asmoro, M. R., Witjaksana, B., & Tjendani, H. T. (2023). Cost And Time Analysis Using Earned Value Method Construction Of Upbjj Building Open University Of Surabaya Phase Ii. In Asian Journal Of Engineering, Social And Health (Vol. 2, Issue 12).
Bambang Siswanto, A., & Afif Salim, M. (2019). Manajemen Proyek Pengadaan Jasa Konstruksi Dengan E-Procurement View Project International Journal Of Civil Engineering And Technology View Project. Https://Www.Researchgate.Net/Publication/339787455
Bonny, A., Oetomo, W., & Marleno, R. (2022). Analysis Of Time And Cost Control Using The Earned Value Method In Well Pad Hilling And Compacting Work In The Pt. Pertamina Hulu Rokan Riau Province. Devotion Journal Of Community Service, 3(14). Https://Doi.Org/10.36418/Dev.V3i14.339
Christy, G. M., Puspasari, V. H., & Nuswantoro, W. (2023). Analisis Pengendalian Biaya Dan Waktu Dengan Metode Nilai Hasil Pada Pembangunan Jalan Simpang Empat Gedung Baru Universitas Palangka Raya. Bentang : Jurnal Teoritis Dan Terapan Bidang Rekayasa Sipil, 11(2), 209–216. Https://Doi.Org/10.33558/Bentang.V11i2.6944
E-Book-Manajemen-Proyek. (N.D.).
Ismail, I., & Darkasyi, D. (2023). Pengendalian Biaya Dan Waktu Pada Proyek Rekonstruksijalan Pante Gurah – Tanohanoe Kecamatan Muara Batu Dengan Metode Earned Value. Jurnal Rekayasa Teknik Dan Teknologi, 7(1). Https://Doi.Org/10.51179/Rkt.V7i1.1827
Iyan Pamungkas, W., & Andreas, A. (2021). Analisis Biaya Dan Waktu Proyek Dalam Proses Kinerja Dengan Menggunakan Metode Earned Value Studi Kasus: Proyek Rancang Bangun Rumah Susun Stasiun Pondok Cina (Analysis Of Project Costs And Time In Process Performance With Using The Earned Value Method Design And Build Project Of Pondok Cina Station Flats ). In Jurnal Artesis (Vol. 1, Issue 2).
Ida Bagus Gede Indramanik, K., Kadek Astariani, N., & Wayan Sudiarsana, Dan I. (2022). Analisa Kinerja Biaya Dan Waktu Menggunakan Metode Konsep Nilai Hasil (Earned Value Concept) Kasus, S., Pembangunan Gedung Ruang Kelas Baru Madrasah Tsanawiyah Negeri, P., Karangasem. In Jurnal Teknik Gradien (Vol. 14, Issue 02). Http://Www.Ojs.Unr.Ac.Id/Index.Php/Teknikgradien
M., Irawan, J., Rijaluddin, A., & Juliar, E. (2019). Pengendalian Konsep Nilai Hasil Pada Proyek Pembangunan Gedung Satpol Pp Kabupaten Majalengka (Vol. 05, Issue 02).
Proboretno, W., Witjaksana, B., & Tjendani, H. T. (2024). Time Performance Analysis On Afv Earthwork In Kedungpeluk Sidoarjo Using The Earned Value Method. Social Sciences And Business (Jhssb) Jhssb | Volume, 3(2). Https://Ojs.Transpublika.Com/Index.Php/Jhssb/
Riduwan, S. P., Witjaksana, B., & Tjendani, H. T. (2023). Cost And Time Analysis Using Earned Value Method In The Construction Of Sports Facilities In Kecamatan Kedewan Kabupaten Bojonegoro. In Asian Journal Of Engineering, Social And Health (Vol. 2, Issue 12). Https://Ajesh.Ph/Index.Php/Gp
Rifatul Muniroh, M. ’, Kempa, M., & Buyang, C. G. (2024). Pengendalian Biaya Dan Waktu Dengan Earned Value Concept Pada Proyek Penataan Bangunan. Jurnal Simetrik, 11(1).
Ritonga, R. A., Megayanti, A., & Herawati, H. (2023). Penerapan Tools Manajemen Proyek Pada Pt. Krakatau It Cilegon. Jika (Jurnal Informatika), 7(2). Https://Doi.Org/10.31000/Jika.V7i2.7674
Slamet Pratama, V. (2022). Analisis Terhadap Biaya Dan Waktu Menggunakan Metode Earned Value Analysis (Eva) Pada Lokasi Proyek Kontruksi.
Sujarwo, A., & Oetomo, W. (2022). Analisis Waktu Dan Biaya Pembangunan Gedung Ikfm, Ips, Ipl Dan Parkir Kendaraan Karyawan. Jurnal Kacapuri : Jurnal Keilmuan Teknik Sipil, 5(1). Https://Doi.Org/10.31602/Jk.V5i1.7527
Published
Issue
Section
License
Copyright (c) 2024 Javan Agustian Setyagraha
This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.