Eduvest � Journal
of Universal Studies Volume 3 Number 1, January, 2023 p- ISSN
2775-3735- e-ISSN 2775-3727 |
||
|
|
|
DEVELOPMENT OF GUIDELINES FOR
IMPLEMENTATION OF BORED PILE FOUNDATION WORK BASED ON RISK ANALYSIS |
|
|
Ikhsan Ramadhan Universitas Indonesia,
Indonesia Email: [email protected] |
|
|
ABSTRACT |
|
|
Foundation specialist contractors already have guidelines for carrying
out bored pile work. However, in its implementation there are risks that
could potentially lead to delays. This is because in carrying out bored pile
work there are risks that are not visible in the ground. Therefore, existing
implementation guidelines need to be developed based on risk. This study aims
to identify and analyze the potential risks that will occur, as well as the
responses that need to be taken in the form of preventive and corrective
actions, so as to develop guidelines for the implementation of risk-based
bored pile work. The method used in this research is a qualitative analysis
and Multi-Attribute Utility Theory (MAUT) analysis. The dominant risk factors
were found, namely the existence of utilities in the ground, improper age of
the tool, collapse of the surface soil around the borehole, changes in the
work implementation schedule from the owner and low labor productivity.
Therefore, the risk response is to carry out Ground Penetrating Radar (GPR)
and area mapping to find out the utilities that are in the ground, replace
tools that are more appropriate, use preliminary casing, carry out careful
planning and bring in an experienced workforce. It is hoped that the guidelines
for implementing risk-based bored pile work can be used by specialist
contractors to minimize the impact of negative risks that may occur in the
implementation of bored pile foundation work. |
|
|
KEYWORDS |
guidelines;
bored pile; risk; delays |
|
|
This
work is licensed under a Creative Commons Attribution-ShareAlike
4.0 International |
|
INTRODUCTION
Foundation
is one of the building structures located at the bottom of a building which
functions to transmit construction loads to the soil layer below the foundation
(Muluk et al., 2020). Foundation in a construction building plays an
important role because it acts as a barrier or supports the load of the
building above it to be passed on to the subsoil below (Matondang et al., n.d.). Bored pile is a drilled pile foundation installed
into the ground by drilling the ground first, then filled with reinforcement
and cast concrete (Hardiyatmo, 2010).
Foundation
work is a vital part of a construction project and has a high complexity in its
implementation, so it is necessary to pay close attention to the risks that
arise at this stage to ensure that the project completion time does not exceed
the time agreed upon by the parties involved in the contract (Assaf & Al-Hejji, 2006). There are two factors that affect foundation work which
are categorized into 2, namely internal factors and external factors. Internal
factors are factors that affect foundation work, namely project planning, land,
foundation construction, materials, labor and
equipment, while external factors are external factors that affect foundation
work, including the project owner (owner), factors from contractors and
consultants, the country's political situation and conditions and the
environment around the project (Puro, 2006). Even though the
foundation specialist contractor already has guidelines for carrying out
foundation work, they still often experience problems or problems in carrying
out work because foundation work has high complexity. Constraints or problems
in the implementation of foundation work include the lack of certainty about
the structures in the ground, unskilled and unproductive workforce, delivery of
materials that are often late, and equipment that cannot work according to plan.
One
example of the phenomenon is the dominant risk factors for bored pile work in
the Jatigede Sumedang Dam
Left Slope Reinforcement project are rain, productivity not as expected,
landslides, surface soil collapse around the borehole and also limited access
roads (Magna et al., 2017). Other dominant risk factors include low labor productivity and delays in ordering tools (Rizkiyanto, 2018). The dominant risk factors for bored pile work that
have an impact on time are tool damage and soil collapse around the drilled
hole [8]. If these dominant factors are not anticipated and managed properly,
they will certainly have an impact on time which can result in delays in
completing work.
PT.
X is a foundation specialist private contractor company in Indonesia. In the
period 2016 - 2020 there are more than 35% of projects annually that experience
delays as in the table below.
Table
1
Bored
Pile Work Delay Data at PT. X in 2016 - 2020
No. |
Years |
Number
of Projects |
Number
of Delays Projects |
Percentage
of Delays Projects |
1 |
2020 |
7 |
3 |
42.86% |
2 |
2019 |
13 |
5 |
38.46% |
3 |
2018 |
15 |
6 |
40.00% |
4 |
2017 |
6 |
3 |
50.00% |
5 |
2016 |
9 |
4 |
44.44% |
Based on project
delay data and bored pile work implementation guidelines at PT. X, it can be
seen that the guidelines for carrying out bored pile work owned by PT. X needs
to be reviewed based on risk analysis so as to minimize negative risks that may
occur. Because the implementation guidelines do not yet have detailed
guidelines on how to anticipate and handle if a risk occurs. The implementation
guideline is still incomplete in terms of handling if there are risks that
occur such as if there is a soil slide in the hole while drilling is in
progress, tool damage and limited access roads which are one of the dominant
risk factors as mentioned in previous studies in on. What actions should be
taken to overcome these dominant risk factors are not listed in the
implementation guidelines currently owned by PT. X.
This research is
important to do considering that the implementation of bored pile foundation
work has several risks such as obstacles that are not visible in the ground,
differences in soil structure from soil investigation data, damage to heavy
equipment and others, which will have a delay impact on the work schedule.
Currently, PT. X does not yet have specific guidelines for anticipating and
dealing with the risks of bored pile work implementation, so it is important to
do research so that various risks can be identified so that they can be used to
develop guidelines for carrying out bored pile work and improve project time
performance.
Risk events are very
important because they can have a direct impact on the performance of work
completion time by PT. X, it is necessary to carry out risk management for
bored pile work to identify and analyze the potential risks that will occur, as
well as the responses that need to be carried out in the form of preventive and
corrective actions. Based on this risk management data, it will then be
developed into a guideline for the implementation of bored pile foundation work
based on risk analysis to improve the implementation guidelines already owned
by PT. X before.
�Project risk management is to increase the
likelihood and/or impact of positive risks and to reduce the likelihood and/or
impact of negative risks, in order to optimize the chances of project success (Marsya, 2017). Qualitative risk analysis is the process of
prioritizing the risks of each project or further action by assessing the
likelihood of their occurrence and their impact and other characteristics (Duncan, 2005). The main benefit of this process is that it focuses
efforts on high priority risks. Risk analysis as one of the research variables
that will be carried out is the dependent variable that is influenced by other
variables. Variables that influence it include the impact and frequency of risk
events that occur, as well as response to risk.
The processes in
developing guidelines for the implementation of risk-based bored pile
foundation work in this study are as follows.
1. Identification of Risk Factors
The risk
identification process in this study will be carried out in the following
order.
a. The first risk identification is carried out by means of
a literature study with the research object being the activity of carrying out
bored pile foundation work as shown in Table 2.
b. The results of the identification of the literature study
were reviewed by experts to find out whether these risk factors could be used
as variables in research to determine the dominant risk factor in the
implementation of bored pile foundation work.
c. After being reviewed by experts, the risk factors were
used as variables in a survey conducted on people who are experienced in the
field of bored pile foundations.
d. The primary data from the survey were then tested and
processed to obtain the dominant risk factors in this study.
Table 2
�Risk
Factors for Bored Pile Foundation Work
No. |
Risk Source Category |
Activity
(Risk Event) |
1 |
Project Planning |
Delay
in design information |
2 |
Errors
in planning and specifications |
|
3 |
Image
approval delays |
|
4 |
Earthworks |
Unstable
subgrade condition |
5 |
There
is ground water disturbance |
|
6 |
Retaining
wall collapse |
|
7 |
Foundation Construction |
Limited
access roads to work |
8 |
Error
in measuring the coordinates of the drill point |
|
9 |
Error
setting excavated land |
|
10 |
Surface
soil collapse around the borehole |
|
11 |
There
are utilities in the ground |
|
12 |
Incorrect
casing installation |
|
13 |
Straight
drilling |
|
14 |
Faulty
stringing |
|
15 |
Error
installing tremi pipe |
|
16 |
Concrete
pouring error |
|
17 |
The
amount and quality of concrete is not appropriate |
|
18 |
Material |
Material
changes in form, function, and specifications |
19 |
Delay
in delivery of materials |
|
20 |
The
volume of material sent to the site is not enough |
|
21 |
Lack
of material storage space |
|
22 |
Labor |
The
scheduling of the workforce needed is not good |
23 |
Low
labor capability |
|
24 |
Lack
of workforce |
|
25 |
Low
labor productivity |
|
26 |
Equipment |
Delays
in ordering tools |
27 |
Delay
in mobilizing equipment to the location |
|
28 |
Insufficient
amount of equipment used |
|
29 |
Tool
age is not worth it |
|
30 |
Equipment
malfunction |
|
31 |
�Owner |
Late
payment from the owner |
32 |
Owner
involvement |
|
33 |
There
is additional work |
|
34 |
Licensing
delays |
|
35 |
There
is a change in the work implementation schedule from the owner |
|
36 |
Factors from Contractors and Consultants |
Error
in interpreting drawings and specifications |
37 |
Ineffective
planning and scheduling |
|
38 |
Poor
qualifications of the contractor's technical staff |
|
39 |
There
are coordination and communication problems with the owner |
|
40 |
Delays
in carrying out final inspection and certification by third parties |
|
41 |
Poor
Quality Assurance / Control |
|
42 |
Poor
planning, implementation and management |
|
43 |
Poor
subcontractor management |
|
44 |
There
is no time control information |
|
45 |
Project
funding is not smooth |
|
46 |
State Political Situation |
There
are changes in policies/regulations that affect project activities |
47 |
Rise
in fuel prices |
|
48 |
Conditions & Environment Around the Project |
Traffic
jams around the project site |
49 |
Problems
with the surroundings |
|
50 |
Weather,
rain or flood |
2. Risk Analysis
In this study the identified risk factors were then
analyzed. using qualitative analysis. Furthermore, determining the level of
risk in each risk identification. The risk level is in the form of a matrix
which is the multiplication of the impact of the risk event and the likelihood
of the risk occurring (risk frequency).
It is difficult for everyone to accept the level of
severity of risk, so it is necessary to convert it into a utility value. Multi
Attribute Utility Theory (MAUT) is a scheme in which the final evaluation of an
object x, V(x) is defined as the weight summed with a value relevant to the
dimension value, the expression commonly used to call it is the utility value (Sch�fer, 2001). MAUT is used to convert from multiple interests into
numerical values on a scale of 0-1 with 0 representing the worst choice and 1
being the best, this allows direct comparison of the various sizes (Puspitasari et al., 2013). Weighting is based on the importance of each existing
criterion, with the largest to the smallest weight with an interval of 0-100 (Hadinata, 2018). Then the sum of each criterion becomes the final value
of each alternative criterion.
3. Risk Response Planning
The next stage is to develop a risk response plan based
on the risk level of the risk analysis matrix. Risk responses can be in the
form of reducing the consequences of the occurrence of risks and reducing the
frequency of possible occurrences of risks. The risk response is composed of
actions to reduce the level of risk from cause and effect if the identified risk
event occurs.
The risk responses obtained in this study were based on
existing literature studies. However, not all responses obtained from the
literature study can be included in the list of responses that must be made.
Therefore, a survey is needed and validated by experts to determine how much
influence each of the proposed risk responses has so that a list of risk
responses that can be implemented will be obtained which will then be developed
to become a guideline for implementing risk-based bored pile foundation work
RESEARCH
METHOD
Risk management on bored pile foundation
work is carried out through several stages. First, identify the risks that have
the potential to affect the time performance of the research object so that the
factors that influence the performance of bored pile foundation work are known.
The second stage is risk analysis through qualitative data analysis so that
risks and responses to these risks can be identified. In the final stage, a
study was carried out to obtain guidelines for the implementation of risk-based
bored pile foundation work to improve performance during construction projects.
Figure
1
Research
Conceptual Framework
RESULTS
AND DISCUSSION
Dominant Risk Factors
To answer RQ 1 regarding the risks that can affect the execution time of
the bored pile foundation work at PT. X. Based on the 50 variables that have
been validated by experts, then data collection is carried out using a
questionnaire on the respondents. After statistical analysis was carried out in
the form of a validity test, there were 18 invalid variables and 32 valid
variables. Then a qualitative risk analysis and MAUT analysis were carried out
which resulted in a risk ranking. Of the 32 variables, there is 1 variable with
an extreme level and 10 variables with a high level which are categorized as
dominant risks that affect the execution time of bored pile foundation work as
can be seen in the following table.
Table 3
�Variable Risk Level
Var.ID |
Variable (Risk Event) |
Final Score |
Rank |
Risk Levels |
X3.5 |
There
are utilities in the ground |
90.67 |
1 |
Extreme |
X6.4 |
Tool age
is not worth it |
69.61 |
2 |
High |
X3.4 |
Surface
soil collapse around the borehole |
66.13 |
3 |
High |
X7.5 |
There is
a change in the work implementation schedule from the owner |
64.13 |
4 |
High |
X5.4 |
Low
labor productivity |
61.74 |
5 |
High |
X5.3 |
Lack of
workforce |
61.68 |
6 |
High |
X2.3 |
Retaining
wall collapse |
58.65 |
7 |
High |
X8.10 |
Project
funding is not smooth |
58.28 |
8 |
High |
X8.7 |
Poor
planning, implementation and management |
56.30 |
9 |
High |
X6.1 |
Delays
in ordering tools |
52.47 |
10 |
High |
X8.9 |
There is
no time control information |
52.37 |
11 |
High |
X9.2 |
Rise in
fuel prices |
49.70 |
12 |
Moderate |
X6.3 |
Insufficient
amount of equipment used |
49.03 |
13 |
Moderate |
X5.2 |
Low
labor capability |
45.76 |
14 |
Moderate |
X6.2 |
Delay in
mobilizing equipment to the location |
45.40 |
15 |
Moderate |
X3.3 |
Error
setting excavated land |
40.15 |
16 |
Moderate |
X4.2 |
Delay in
delivery of materials |
39.46 |
17 |
Moderate |
X5.1 |
The
scheduling of the workforce needed is not good |
38.49 |
18 |
Moderate |
X8.8 |
Poor subcontractor
management |
37.42 |
19 |
Moderate |
X1.2 |
Errors
in planning and specifications |
32.45 |
20 |
Moderate |
X8.6 |
Poor
Quality Assurance / Control |
31.81 |
21 |
Moderate |
X1.1 |
Delay in
design information |
31.48 |
22 |
Moderate |
X8.3 |
Poor
qualifications of the contractor's technical staff |
29.91 |
23 |
Moderate |
X3.11 |
The
amount and quality of concrete is not appropriate |
27.18 |
24 |
Moderate |
X3.9 |
Error
installing tremi pipe |
26.58 |
25 |
Moderate |
X3.7 |
Straight
drilling |
19.74 |
26 |
Low |
X8.2 |
Ineffective
planning and scheduling |
18.54 |
27 |
Low |
X8.4 |
There
are coordination and communication problems with the owner |
18.04 |
28 |
Low |
X4.1 |
Material
changes in form, function, and specifications |
16.45 |
29 |
Low |
X3.6 |
Incorrect
casing installation |
16.34 |
30 |
Low |
X3.8 |
Faulty stringing |
15.51 |
31 |
Low |
X8.5 |
Delays
in carrying out final inspection and certification by third parties |
2.67 |
32 |
Low |
Risk Responses
To answer RQ 2 regarding what responses need to be done to manage the
risk so that when the bored pile foundation work is carried out at PT. X is not
too late. Furthermore, an analysis of the risk response to the dominant risk
factors consisting of causes, effects, preventive actions and corrective
actions will be carried out by validating the results of the literature study by
experts who have experience in carrying out bored pile work. Data on risk
causes, risk consequences and risk responses to dominant risks based on the
results of a literature study can be seen as follows.
Table 4
�Risk Responses
Var.ID |
Variable
(Risk Event) |
Preventive
Measures |
Corrective
Action |
X3.5 |
There are utilities in
the ground |
Can do Ground Penetrating
Radar (GPR) first to find out objects buried in the ground and it is
necessary to carry out an inventory of utilities in the work area |
Perform mapping of areas
where there are utilities in the ground, then coordinate with supervisors and
planners to review the foundation layout |
X6.4 |
Tool age is not worth it |
Check the feasibility and
age of the equipment to be used before being mobilized to the location |
Make a more appropriate
tool replacement, and immediately send the replacement tool to the location |
X3.4 |
Surface soil collapse
around the borehole |
Carry out ground
investigations accurately |
Can use preliminary
casing to prevent soil collapse around the borehole |
X7.5 |
There is a change in the
work implementation schedule from the owner |
Do more mature planning
in accordance with the wishes and needs of the owner |
Propose additional
implementation schedules to the owner and make adjustments to schedule
planning |
X5.4 |
Low labor productivity |
Conduct coaching and
debriefing to workers before the implementation of work |
Bringing in an
experienced workforce to mobilize workers who are still lacking in
experience, as well as increasing working time to catch up on work progress |
X5.3 |
Lack of workforce |
Calculate and evaluate
the volume of work appropriately so that the number of workers needed is
appropriate and provide workers who are experienced and competent in their
fields |
Increase the number of
workers and work time, as well as clear supervision from the foreman or
supervisor from the contractor |
X2.3 |
Retaining wall collapse |
Carry out better and more
accurate planning, and use competent personnel according to their areas of
expertise |
Re-check the design, and
make improvements |
X8.10 |
Project funding is not
smooth |
The contractor must carry
out a cost management plan before starting the project to complete the work |
Evaluate the cost of
carrying out the work with the initial planning |
X8.7 |
Poor planning,
implementation and management |
Recruiting skilled
workers in accordance with their areas of expertise |
Recruit permanent
professional staff for each expertise in project implementation and routinely
carry out regular coordination to evaluate the implementation of work |
X6.1 |
Delays in ordering tools |
Scheduling properly the
procurement and ordering of tools, as well as making schedules for detailed
tools |
Communicate continuously
with the procurement of equipment |
X8.9 |
There is no time control
information |
Make an agreement between
the contractor and the owner regarding reporting on the progress of work
implementation to monitor the time of completion of the work |
Conduct routine
coordination meetings every week to evaluate work progress and discuss
implementation problems/obstacles in the field that may affect work
completion time |
Development of Implementation
Guidelines
To answer RQ 3 regarding the development of guidelines
for the implementation of bored pile foundation work based on risk analysis at
PT. X. Development of guidelines for implementing risk-based bored pile
foundation work is carried out by directly validating the results of data
processing and determining the response to the dominant risk in bored pile
foundation work based on answers from RQ 1 and RQ 2 so that a new guideline is
obtained in the implementation of effective bored pile work used because it can
minimize risk and can improve time performance as can be seen in the following
table.
�
Table 5
Guidelines Development Recapitulation
No. |
Variable (Risk Event) |
Development Guidelines |
1 |
There
are utilities in the ground |
1. Conduct
a Ground Penetrating Radar (GPR) first to find out objects buried in the
ground and it is necessary to carry out an inventory of utilities in the work
area before carrying out work (Arief & Sumargana, n.d.). 2. If
utilities are found in the ground, it is necessary to map the area. 3.
Then coordinate with the owner, planner
and supervisor to review the bored pile layout based on the results of
mapping the utility area in the ground. |
2 |
Tool age
is not worth it |
If the
equipment has arrived at the destination location, it is necessary to
re-check the number and condition of the equipment, if there is a shortage
and equipment is damaged due to the mobilization process, coordination is
immediately carried out with the equipment procurement party. |
3 |
Surface
soil collapse around the borehole |
Conduct
a soil investigation if there is no soil data at the work location (Prayogo & Saptowati, 2017) |
4 |
There is
a change in the work implementation schedule from the owner |
1. Coordinate
with the owner regarding work implementation schedules, payments and design
information. 2. Planning
the time and cost control of the implementation of the work. |
5 |
Low
labor productivity |
Planning
the qualifications and the number of workers needed. |
6 |
Lack of
workforce |
Planning
a schedule for evaluating the ability and number of workers. |
7 |
Retaining
wall collapse |
Check
for potential collapse of retaining walls. |
8 |
Project
funding is not smooth |
Perform
time and cost control planning for the implementation of the work. |
9 |
Poor
planning, implementation and management |
1. Planning
to control time and costs for the implementation of the work. 2. Planning
the qualifications and the number of workers needed. |
10 |
Delays
in ordering tools |
1. Planning
a delivery schedule and calculating the number of tool requirements. 2. Place an
order for tools based on the planned delivery schedule and the amount that
has been made. 3.
Monitoring the mobilization of equipment
so that it is according to the delivery schedule by coordinating with the
expeditionary party. |
11 |
There is
no time control information |
Planning
a coordination meeting schedule with the owner to monitor the progress of the
implementation of the work and the constraints that occur both technical and
non-technical. |
12 |
Late
payment from the owner |
1. Coordinate
with the owner regarding work implementation schedules, payments and design
information. 2. Planning
a coordination meeting schedule with the owner to monitor the progress of the
work implementation and the constraints that occur, both technical and
non-technical (Sebayang et al., 2018) |
13 |
Delay in
delivery of concrete |
Planning
the delivery schedule for materials such as iron and concrete in accordance
with the specifications and quantities needed. |
CONCLUSION
Based on the results of research
on the development of bored pile work implementation guidelines, it can be
concluded as follows:
The dominant risk factor for bored
pile work. Based on the results of this study it can be concluded that in the
implementation of bored pile work there is a dominant risk factor that has an
impact on time performance.
Formulation of risk response as a
strategy for managing dominant risk factors in the implementation of bored pile
work, in the form of data on risk causes, risk consequences and risk responses
in the form of preventive actions and corrective actions on dominant risks
which will serve as the basis for developing guidelines for implementing bored
pile foundation work.
Guidelines for the implementation
of bored pile foundation work based on risk, which is a development of existing
guidelines based on the results of risk analysis that has been carried out to
obtain dominant risks that affect time performance, so that a risk response is
obtained to manage these dominant risks during implementation of bored pile
foundation work.
REFERENCES
Arief, M., & Sumargana, L.
(N.D.). Penggunaan Metode Ground Penetrating Radar (Gpr) Untuk
Identifikasi Utilitas Bawah Tanah. Prisma Fisika, 9(3), 244�248.
Assaf, S. A., & Al-Hejji,
S. (2006). Causes Of Delay In Large Construction Projects. International
Journal Of Project Management, 24(4), 349�357.
Duncan, W. (2005). Project
Management Institute. A Guide To The Project Management Body Of Knowledge.
Automated Graphic Systems, Charlotte, Nc, Usa.
Hadinata, N. (2018).
Implementasi Metode Multi Attribute Utility Theory (Maut) Pada Sistem Pendukung
Keputusan Dalam Menentukan Penerima Kredit. Jurnal Sisfokom (Sistem
Informasi Dan Komputer), 7(2), 87�92.
Hardiyatmo, H. C. (2010). Analisis
Dan Perancangan Fondasi Bagian Ii. Gadja Mada University Press, Yogyakarta.
Magna, M. T., Hartono, W.,
& Sugiyarto, S. (2017). Analisis Risiko Konstruksi Struktur Bore
Pile Pada Proyek Dengan Metode Analytical Hierarchy Process (Ahp). Matriks
Teknik Sipil, 5(2).
Marsya, L. (2017). Analisis
Risiko Pekerjaan Pengecoran Pondasi Bore Pile Diameter 1200 Mm Pada Proyek
Jalan Tol Jakarta-Cikampek Ii (Elevated) Sta 9+ 500-Sta 28+ 000 Terhadap Waktu.
Universitas Mercu Buana Jakarta.
Matondang, Z., Siagian, V. L.
B., & Putra, A. N. (N.D.). Konstruksi Bangunan Gedung:
Tutorial Pembuatan Elemen Konstruksi Bangunan Gedung.
Muluk, M., Hamid, D., &
Santi, M. (2020). Studi Perbandingan Pondasi Tiang Pancang Dengan
Pondasi Bore Pile (Studi Kasus: Pelaksanaan Pembangunan Pondasi Tower Grand
Kamala Lagoon-Bekasi). Jurnal Teknik Sipil Itp, 7(1), 26�33.
Prayogo, K., & Saptowati,
H. (2017). Penyelidikan Struktur Dan Karakteristik Tanah Untuk
Desain Pondasi Iradiator Gamma Kapasitas 2 Mci. Jurnal Perangkat Nuklir,
10(1).
Puro, S. (2006).
Scoring Points: Politicians, Activists, And The Lower Federal Court Appointment
Process. Perspectives On Political Science, 35(1), 54.
Puspitasari, N. B., Rumita,
R., & Pratama, G. Y. (2013). Pemilihan Strategi Bisnis Dengan
Menggunakan Qspm (Quantitative Strategic Planning Matrix) Dan Model Maut (Multi
Attribute Utility Theory)(Studi Kasus Pada Sentra Industri Gerabah Kasongan,
Bantul, Yogyakarta). J@ Ti Undip: Jurnal Teknik Industri, 8(3),
171�180.
Rizkiyanto, B. (2018).
Identifikasi Risiko Keterlambatan Pekerjaan Pondasi Bore Pile Diameter 1000
Mm Pada Proyek Gedung Nines Plaza & Residence At Cbd Serpong.
Universitas Mercu Buana Jakarta.
Sch�fer, R. (2001).
Rules For Using Multi-Attribute Utility Theory For Estimating A User�s
Interests. Ninth Workshop Adaptivit�t Und Benutzermodellierung In
Interaktiven Softwaresystemen, 8�10.
Sebayang, E. M., Rahardjo, H.
A., & Dinariana, D. (2018). Pengelolaan Risiko Proyek Gedung
Bertingkat Pada Pt. Xyz Di Jakarta Terhadap Kinerja Waktu. J. Tek. Sipil,
25(3), 229.