How to cite:
Mardiaman , Daud Surbakti . (2022). Study Of Progress Difference
On Building Construction Works. Journal of Eduvest . Vol 2 (9): Page
E-ISSN:
2775-3727
Published by:
https://greenpublisher.id/
Eduvest – Journal of Universal Studies
Volume 2 Number 10, October, 2022
p- ISSN 2775-3735 - e-ISSN 2775-3727
STUDY OF PROGRESS DIFFERENCE ON BUILDING
CONSTRUCTION WORKS
Mardiaman
1
, Daud Surbakti
2
Universitas Tama Jagakarsa
1
Universitas Mpu Tantular, Indonesia
2
ABSTRACT
The progress of construction work has different deviations at a
certain point in time. Various factors cause inequality. A
positive progress deviation indicates that construction work is
completed faster where the progress of the plan is lower than
the actual one, otherwise it is said to be late if it is negative.
The uncertain nature of construction work causes there are 3
(three) scenarios of possible progress deviation values, so that
these three values form one expected progress deviation value.
A deviation of value greater than negative 10% for a duration
from 0 to 70% is categorized as a critical contract. The purpose
of this study was to determine the deviation of the progress of
29 construction works. Data collection was carried out on 29
construction works that had been carried out. The data is taken
directly from the contractor. The results of data analysis
showed that at 10% D, 11 construction works with poor
performance were obtained. Information was also obtained
that the construction work No. 12 have critical contracts (-
11,773). Furthermore for the current construction work 30%D.
50% D and 70% D number of poorly performing construction
works 12; 10; and 9. The value of the largest positive progress
deviation is 15,362 at the 70% time point D. The expected value
of the largest positive progress deviation is positive 1,763. By
knowing the expected negative progress value, the contractor
must exercise control as soon as possible before the contract
expires. Acceleration can be done on activities that are on the
critical path.
KEYWORDS
Construction Work, Deviation Of Progress, Yield Value,
Expected Value, Uncertainty
This work is licensed under a Creative Commons
Attribution- ShareAlike 4.0 International
Mardiaman , Daud Surbakti
Study of Progress Difference on Building Construction Works.
INTRODUCTION
Work construction often experience delays that cause losses to contractors ,
consultants and owners good that time and money (Hassan et al., 2016) . Type
profession construction miscellaneous . one _ delivered is profession building
storied . High -rise buildings in general shared Becomes two , building graded low
and building graded high .
From the side contractor , lost time cause source power no could quick
drawn from location project . This cause happening swelling cost . Lateness be
measured with no the fulfillment of the work progress that has been planned in
schedule parent . Many factors cause _ why lateness occur (Mardiaman &
Indriasari, 2021) ; (Hassan et al., 2016) ; ( Shahsavand et al., 2018) . Lateness often
caused by contractor no capable provide appropriate funds with the progress of the
plan that has been compiled . Often an advance payment has been found given
diverted to project another . This occur because contractor work more from one
profession construction in time simultaneously . For prevent lateness contractor
must To do analysis the cause (Shahsavand et al., 2018) . Besides that must
identified factonrya (Asmi & Pratama, 2016) Stability finance must available for
finance profession construction . According to (Mardiaman, 2020) that criteria
stability finance Becomes most important criteria for choose contractor so that
profession construction can success . one _ success profession construction seen
from side suitability time plan .
Work progress construction could seen every period time . generally
evaluated every week at the time meeting weekly . Meeting weekly generally
attended element owners , consultants and contractors . On every meeting all
problem about achievement of progress and weekly targets discussed by together
according to ability . Target time customized with availability source power and
condition field. However resources that should provided no fulfill good from side
amount and quality.
In practice , progress can be experience deviation , fine positive and negative
. The deviation of progress is difference between plan and actual progress . The size
deviation is score results profession construction , Yield value Becomes criteria in
evaluation value performance _ vary . This value must traced (Amruta B. Vyas &
BV Birajdar, 2016) . Yield value is one _ technique control profession construction
(Suharto, 2007) ; ( Bhosekar & Vyas, 2012) . Time and costs incurred is reflection
achievement progress (Huda et al., 2018) .
Because of the nature profession construction that is not certain then
progress will be character probability , can fulfilled and not fulfilled . more and
more information obtained so level probability the more high , worth zero until with
one . There is progress pessimistic , most likely and optimistic , so that from all
three will shape one score hope for progress (Mardiaman & Kusuma, 2021) .
The purpose of this study was to determine the deviation of the progress of
29 construction works.