How to cite:
Mardiaman , Daud Surbakti . (2022). Study Of Progress Difference
On Building Construction Works. Journal of Eduvest . Vol 2 (9): Page
E-ISSN:
2775-3727
Published by:
https://greenpublisher.id/
Eduvest Journal of Universal Studies
Volume 2 Number 10, October, 2022
p- ISSN 2775-3735 - e-ISSN 2775-3727
STUDY OF PROGRESS DIFFERENCE ON BUILDING
CONSTRUCTION WORKS
Mardiaman
1
, Daud Surbakti
2
Universitas Tama Jagakarsa
1
Universitas Mpu Tantular, Indonesia
2
ABSTRACT
The progress of construction work has different deviations at a
certain point in time. Various factors cause inequality. A
positive progress deviation indicates that construction work is
completed faster where the progress of the plan is lower than
the actual one, otherwise it is said to be late if it is negative.
The uncertain nature of construction work causes there are 3
(three) scenarios of possible progress deviation values, so that
these three values form one expected progress deviation value.
A deviation of value greater than negative 10% for a duration
from 0 to 70% is categorized as a critical contract. The purpose
of this study was to determine the deviation of the progress of
29 construction works. Data collection was carried out on 29
construction works that had been carried out. The data is taken
directly from the contractor. The results of data analysis
showed that at 10% D, 11 construction works with poor
performance were obtained. Information was also obtained
that the construction work No. 12 have critical contracts (-
11,773). Furthermore for the current construction work 30%D.
50% D and 70% D number of poorly performing construction
works 12; 10; and 9. The value of the largest positive progress
deviation is 15,362 at the 70% time point D. The expected value
of the largest positive progress deviation is positive 1,763. By
knowing the expected negative progress value, the contractor
must exercise control as soon as possible before the contract
expires. Acceleration can be done on activities that are on the
critical path.
KEYWORDS
Construction Work, Deviation Of Progress, Yield Value,
Expected Value, Uncertainty
This work is licensed under a Creative Commons
Attribution- ShareAlike 4.0 International
Mardiaman , Daud Surbakti
Study of Progress Difference on Building Construction Works.
INTRODUCTION
Work construction often experience delays that cause losses to contractors ,
consultants and owners good that time and money (Hassan et al., 2016) . Type
profession construction miscellaneous . one _ delivered is profession building
storied . High -rise buildings in general shared Becomes two , building graded low
and building graded high .
From the side contractor , lost time cause source power no could quick
drawn from location project . This cause happening swelling cost . Lateness be
measured with no the fulfillment of the work progress that has been planned in
schedule parent . Many factors cause _ why lateness occur (Mardiaman &
Indriasari, 2021) ; (Hassan et al., 2016) ; ( Shahsavand et al., 2018) . Lateness often
caused by contractor no capable provide appropriate funds with the progress of the
plan that has been compiled . Often an advance payment has been found given
diverted to project another . This occur because contractor work more from one
profession construction in time simultaneously . For prevent lateness contractor
must To do analysis the cause (Shahsavand et al., 2018) . Besides that must
identified factonrya (Asmi & Pratama, 2016) Stability finance must available for
finance profession construction . According to (Mardiaman, 2020) that criteria
stability finance Becomes most important criteria for choose contractor so that
profession construction can success . one _ success profession construction seen
from side suitability time plan .
Work progress construction could seen every period time . generally
evaluated every week at the time meeting weekly . Meeting weekly generally
attended element owners , consultants and contractors . On every meeting all
problem about achievement of progress and weekly targets discussed by together
according to ability . Target time customized with availability source power and
condition field. However resources that should provided no fulfill good from side
amount and quality.
In practice , progress can be experience deviation , fine positive and negative
. The deviation of progress is difference between plan and actual progress . The size
deviation is score results profession construction , Yield value Becomes criteria in
evaluation value performance _ vary . This value must traced (Amruta B. Vyas &
BV Birajdar, 2016) . Yield value is one _ technique control profession construction
(Suharto, 2007) ; ( Bhosekar & Vyas, 2012) . Time and costs incurred is reflection
achievement progress (Huda et al., 2018) .
Because of the nature profession construction that is not certain then
progress will be character probability , can fulfilled and not fulfilled . more and
more information obtained so level probability the more high , worth zero until with
one . There is progress pessimistic , most likely and optimistic , so that from all
three will shape one score hope for progress (Mardiaman & Kusuma, 2021) .
The purpose of this study was to determine the deviation of the progress of
29 construction works.
Eduvest Journal of Universal Studies
Volume 2, Number 9 , September, 2022
1978
http://eduvest.greenvest.co.id
Weight Work
Work item weight obtained dengsn compare between ` cost start of work
item certain with total cost (Mardiaman, 2022)

(1)
x
i
= Cost activity type i
= Total project cost
Curve weight cumulative basically _ shape S curve . At first achievements
percentage project rather small increase , then will the more increase fast because
condition work and resources power many deployed to location . Achievement of
progress in the end slow down because start occur withdrawal source power and
work almost done worked on . At the end project the total progress achieved is 100
percent (Figure 1).
Figure 1. The formed S curve of weekly progress
Deviation of Progress
The deviation of progress is difference Among progress plan and actual .
Deviation value could positive and negative (Figure 2).
Figure 2. Deviation plan and actual .
Mardiaman , Daud Surbakti
Study of Progress Difference on Building Construction Works.
Draft Probability in Work Construction
Project progress results no sure , where is the value will different between
job construction . In general shaped asymmetrical and is called beta curve (Figure
3).
frekuensi
5 D
E
4 C
F
3 B
G
2 A H
I
1 J
K
a b c d e f g h i j k
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Figure 3. curve distribution of work progress construction
After determine estimation the numbers a, b and m then next formulated
connection third number the Becomes one a number called pe or period expected
time . _ Pe number is the average if activity the done by repeated in large amount .
_ the progress that expected formulated :
p
e
= (a + 4m + b)/6 ( 2)
a = pessimistic progress taken the smallest .
m = progress most likely taken as average
b = optimistic progress take the biggest
density
probabilitas
a m te b
Figure 4. curve distribution asymmetric (beta) with a, m and b
Approach score hope consider that score hope for score results depend on
estimate three number estimation .
Eduvest Journal of Universal Studies
Volume 2, Number 9 , September, 2022
1980
http://eduvest.greenvest.co.id
Contract Critical
Part five chapter 36 of candy PUPR No. 14 of 2020 regarding standards and
guidelines provision service construction mention that down payment given by a
maximum of 30% of score contract for effort small , maximum 20% for
qualification effort medium and large . While for contract year the biggest plural
given 15% ( Regulation of the Minister of Public Works and Public Housing of the
Republic of Indonesia Number 07/PRT/M/2019 concerning Standards and
Guidelines for Procurement of Construction Services Through Providers, 2020) .
With advance payment _ expected profession construction no experience contract
critical . In accordance with PU Ministerial Decree No. 07/PRT/M/2011 PK book
06A-Chapter VII B6 Number 39.2, contract declared critical when :
1. Period I ( plan physique implementation 0% - 70% of contract ), realization
physique implementation late more big 10% of plan .
2. Period II ( plan physique execution 70% - 100% of contract ), realization
physique implementation late more big 5% of plan . Study determine big
deviation of work progress construction in the period of 10%, 30%, 50%, 70%
of duration profession construction and big deviation of progress in the period
of 10%, 30%, 50%, 70% of duration profession construction .
On some profession construction occur contract critical so that need
conducted show case meeting (SCM). Implementation of SCM with inviting office
maker commitment (PPK), contractor , consultant supervisor . At the PPK meeting
, they asked explain reason lateness work and ways speed up profession in
accordance with ability them and still received the reason .
Contractor make plan work with a certain progress target so that less
progress _ from 10% for period 1 ( plan physique implementation 0% - 70% of
contract ).
RESEARCH METHOD
Research data collected _ in the form of primary and secondary data .
Secondary data in the form of timetable time plan and actual . There are as many as
29 jobs collected construction _ start 2016 to 2021. Duration _ profession
construction start from 18 months up to 64 months . Schedule data collected from
selected contractors and consultants _ with purposive sampling method . Due to
duration profession construction different , then conducted equation time based on
percentage times total duration time for every profession construction . The average
deviation of progress uses formula 5.

(5)
Yield value hope deviation of work progress construction calculated with
step following :
Big deviation of progress every week all profession construction ,
deviation , average, maximum from all profession construction
Count score hope the deviation of the progress of hope profession
construction
Big score results deviation progress hope using formula 2:
 󰇛  󰇜󰇛󰇜
Mardiaman , Daud Surbakti
Study of Progress Difference on Building Construction Works.
Count deviation of progress at time activity in progress for 10% of
duration plan .
Count deviation progress at the moment activity in progress for 30% of
duration plan .
Count deviation progress at the moment activity in progress for 50% of
duration plan .
Count deviation progress at the moment activity in progress for 50% of
duration plan .
RESULTS AND DISCUSSION
From result processing of collected data obtained that the progress of each
profession construction different different at the point time certain . Progress value
there are positive and negative . Deviation worth positive signify that profession
construction perform good , on the other hand if deviation worth negative state that
profession construction perform bad . `
In table 1 it is explained that there are 4 periods rated time _ quantity
deviation progress that is, at the point time profession construction 10%, 30%, 50%
and 70% of plan physique implementation contract . At the time of 10%D obtained
11 projects perform bad be marked with the deviation of progress is worth negative
, Next for profession 30% constructionD . 50%D and 70%D perform bad in a row
12; 10; and 9. On the contrary amount profession performance construction _ good
with score positive progress deviation at 10%D , 30%D. 50%D and 70%D
respectively as many as 8, 17, 19 and 20.
Table 1. Big Deviation of Progress at 29 Jobs Construction
pack.
Construction
S10%D
S30%D
S50%D
S70%D
1
0.375
1.029
-3.418
0.458
2
0.375
1.029
-3.418
0.458
3
0.200
-1,800
-0.100
4,600
4
0.090
0.240
0.420
0.370
5
0.200
-1,800
-0.100
4,600
6
-0.209
-2.088
2,725
1.865
7
-0.110
0.540
-0.080
0.100
8
-2.419
6.104
2.133
2,283
9
-0.110
-0.460
-0.380
0.400
10
-2.419
6.104
2.133
2,283
11
0.090
-0.960
-1.010
-1,600
12
-0.278
-11,773
-9.010
4.506
13
-0.920
-0.640
0.040
-8.380
14
-0.940
0.180
0.300
-7,580
15
0.400
1,200
0.000
-0.300
16
0.150
-0.300
0.050
-7,500
17
-0.574
-0.533
-5.045
-4.151
18
0.090
-0.530
0.650
-0.200
19
-0.899
-1.087
2.447
0.581
20
1,670
2.93
1.4
-1,500
Eduvest Journal of Universal Studies
Volume 2, Number 9 , September, 2022
1982
http://eduvest.greenvest.co.id
21
0.462
6.686
3.297
6.897
22
5.710
9,811
7.231
0.403
23
4.152
6,529
3.072
2.201
24
2.184
7.482
1,099
2,942
25
0.100
9.754
9.006
15,362
26
1.016
1.073
1.216
2,915
27
-0.765
1971
-8,870
-7,430
28
0.287
-8,807
7.628
2.851
29
0
0
0
0
Source data processing
For hopeful progress when 10 %D is obtained 0.73, Next for profession 30%
constructionD . 50%D and 70%D perform bad consecutively 0.362; 0.285 and
1564. Work the best construction performance is profession construction 25th with
_ score positive progress deviation biggest 15,362 at S70%D.
Table 2. Job Expectation Progress Construction
S% D
a
m
b
SPe
S10% D
-2.419
0.273
5.710
0.730
S30% D
-11,773
1.034
9,811
0.362
S50% D
-9.010
0.429
9.006
0.285
S70%D
-8.380
0.601
15,362
1.564
Source data processing
Table 1. explains that of 29 jobs construction there is 1 job great
construction _ deviation progress more from negative 10% i.e. negative 11.773%
so that enter category contract critical . Contract critical this need controlled . Big
small deviation is known after monitoring and reporting .
Based on reporting , project 12th need _ conducted acceleration with stage
deployment resource optimally . At the moment S30%D looks occur there is
progress progress. Be marked with happening subtraction deviation to (-9.01) and
at S50%D to (4.506).
At S70%D value deviation already Becomes positive 4,506. This thing state
that profession construction this in the end perform good . Work this experienced 1
time contract critical because progress worth more small of (-10%).
Discussion
Big deviation of progress between one profession construction with others
_ of course just fickle big , because of course various factor influence success
profession construction . Influencing factors _ can from inside and outside . Factor
outside difficult intervened temporary for internal factors can intervened .
Acceleration easy conducted if the problem from in in other words acceleration can
done . one _ the method with increase working hours (Frederika, 2010) . Various
factor as reason delay in progress. This thing already proven from study before
(Milah et al., 2019) ; ( Gerawork Jembere et al., 2020) .
On project 12th happened _ contract critical because deviation of progress
is worth (- 11.773) so that Required performed SCM. S how cause meeting (SCM)
was held because big more progress deviation of (-10%). For reduce big deviation
Mardiaman , Daud Surbakti
Study of Progress Difference on Building Construction Works.
worth negative need conducted efforts maximum . Priority solution profession
certain that can done by together must noticed . It is also necessary to pay attention
dependent work one each other on the track critical. Speed up work on track critical
is a good strategy.
Of course just in speed up work on track critical need conducted with add
power work , add tool . no in accordance achievements profession construction
often occur because not enough consistency contractor carrying out job. There are
various the cause that is happening planning that doesn't in accordance with
condition field . Of course just this cause happening addition time for correct repeat
planning . Contractor no put source power in accordance with needs join donate
happening delay . Understanding to method work also suspected as contributor
lateness implementation construction .
Method work actually already proposed by the contractor at the time submit
offer project at the moment auction. However, many only limited theory because
no truly visit field. At the moment meeting preparation the field (pre construction
meeting) has also been discussed. Election contractor by right on time auction
determine in success project.
CONCLUSION
Based on discussion previously so concluded namely : Work construction
character no certain with existence difference deviation of progress in the case
studied . Various factor the uncertainty that affects good external and internal to
existence uncertainty There are 3 (three) scenarios possibility occur the deviation
of progress is pessimistic, most likely and optimistic that make up one score hope.
REFERENCES
Amruta B. Vyas, & B. V. Birajdar . (2016). Tracking of Construction Projects by
Earned Value Management. International Journal of Engineering Research
And, V5(03), 829831. https://doi.org/10.17577/ijertv5is031318
Asmi, A., & Pratama , JCS (2016). Identification Factors Lateness In Project
Construction In Jakarta. Journal.Umj.Ac.Id / Index.Php / Semnastek ,
November, 112.
Bhosekar , SK, & Vyas, G. (2012). Cost Controlling Using Earned Value Analysis
in Construction Industries. International Journal of Engineering and
Innovative Technology, 1(4), 324332.
https://www.researchgate.net/profile/Gayatri_Vyas2/publication/26528533
9_Cost_Controlling_Using_Earned_Value_Analysis_in_Construction_Ind
ustries/links/553b16c50cf2c415bb08ffcf/Cost-Controlling-Using-Earned-
Industries-Astruction-Value.pdf
Frederika, A. (2010). Analysis Conversation Implementation With Adding
Optimum Working Hours To The Project Construction ( Study Case : Super
Villa Development Project , Peti Tenget-Badung ) Ariany Frederika. 14(2),
113126.
Geawork Jembere , M., Bewket Mitikie , B., & Kelemework Yigzaw , E. (2020).
Performance Evaluation of Housing Construction Project, Using Earned
Value Analysis; the Case of 20/80 Condominium Addis Ababa Bole Arabsa
Eduvest Journal of Universal Studies
Volume 2, Number 9 , September, 2022
1984
http://eduvest.greenvest.co.id
Site. American Journal of Engineering and Technology Management, 5(4),
69. https://doi.org/10.11648/j.ajetm.20200504.12
Hassan, H., Mangare , JB, & Pratasis , PAK (2016). Factors reason delay on project
construction and alternatives solution ( study ) case : in Manado Town
Square III). Journal Civil Statics Vol.4, 4(11), 657664.
Huda, K., Mulyadi , L., & Santosa , A. (2018). Analysis of time and cost
performance with earned value method in lecture building project
development of nutrition department at East Kalimantan health polytechnic.
International Journal of Scientific and Technology Research, 7(2), 203207.
Mardiman . (2020). Determining Weight Criteria/ Sub-Criteria In Selecting Public
Construction Work Contractor. Palarch's Journal Of Archeology Of
Egypt/Egyptology, 17(9), 94859495.
https://archives.palarch.nl/index.php/jae/article/view/5910/5786
Mardiman . (2022). Planning and Scheduling Construction (1st ed.). Indonesian
KBM.
Mardiaman , & Indriasari . (2021). Factors The Main Determinants of Late Work
Construction Factory ( Study Case : Cikarang Area Factory ). CENTECH
2020 E-Journal, 2(1), 111. http://ejournal.uki.ac.id/index.php/cen
Mardiaman , & Kusuma, E. (2021). Study of Progress Expected Results Based on
Percentage of Construction Work Plan Duration. Journal of Civil
Engineering , Lamongan Islamic University , 6(2), 167.
https://doi.org/10.30736/cvl.v6i2.628
Milah , S., Nurmayadi , D., & Hendardi , AR (2019). Analysis Project Time Control
Construction Using Earned Value Concept (EVC) and Critical Path Method
(CPM). Journal Civil Engineering Science , 1(1), 114.
Minister of Work Regulation Public and Public Housing of the Republic of
Indonesia Number 07/PRT/M/2019 Regarding Standards And Guidelines
Construction Services Procurement Through Provider , State Gazette of the
Republic of Indonesia Year 2019 Number 319. Jakarta (2020).
Shahsavand , P., Marefat , A., & Parchamijalal , M. (2018). Causes of delays in
construction industry and comparative delay analysis techniques with SCL
protocol. Engineering, Construction and Architectural Management, 25(4),
497533. https://doi.org/10.1108/ECAM-10-2016-0220
Suharto, D. (2007). Earned Value Method For Control (Study Case City Hall
Building Project Surak). Journal of Civil Engineering UNS Surakarta.