Eduvest �
Journal of Universal Studies Volume 4
Number 9, September, 2024 p- ISSN
2775-3735- e-ISSN 2775-3727 |
||
|
|
|
ANALYSIS OF THE EARNED VALUE METHOD ON THE ROAD AND BRIDGE
PRESERVATION PROJECT IN SITUBONDO-KETAPANG-BANYUWANGI |
|
|
Javan Agustian Setyagraha, Budi Witjaksana,
Hanie Teki Tjendani 1,2,3 Universitas
17 Agustus 1945 Surabaya, Indonesia Email: [email protected],
[email protected], [email protected] |
|
|
ABSTRACT |
|
|
The implementation of the Situbondo � Ketapang � Banyuwangi Road and
Bridge Preservation Project experienced changes in the area being worked on,
requiring additional design. Issues arose when the overlay asphalt mix work
was halted to await test results for Aspal Modiv PG � 70 from the Pusjatan
Bandung Road Materials Laboratory, causing a delay in the 40th week by
-0.813%. Delays primarily occurred in the AC - WC and AC - BC asphalt work,
affecting project performance. A cost and time analysis was necessary to
address this issue. The Earned Value Method (EVM) was used to determine the
project's duration and cost until initial handover. The study results
indicated that the project cost performance with a CPI > 1 was good, but
an SPI of 0.983 < 1 indicated delays. The estimated final project cost is
Rp 112,439,121,070.91, with an estimated completion time of 453 days, 3 days
longer than the planned schedule. |
|
|
KEYWORDS |
Earned Value Method, Project Performance, Project
Cost |
|
This work is licensed under a Creative Commons
Attribution-ShareAlike 4.0 International |
|
INTRODUCTION
Infrastructure development plays an important role in driving economic growth, both at the national and regional levels. Adequate infrastructure not only increases economic activity and business growth, but also reduces unemployment, alleviates poverty, and improves people's welfare. Therefore, the Government of Indonesia is committed to continuously improving infrastructure development (Kurniawati et al., 2022). Construction projects are a key element in infrastructure development. In Indonesia, many construction projects often experience delays, which is a classic problem in almost every project. The obstacles faced in project implementation often cause delays, so that the project does not run according to plan (Natalia et al., 2021).
In line with the government's efforts to provide adequate road infrastructure, the Situbondo - Ketapang - Banyuwangi Road and Bridge Preservation project is currently being implemented. This project is part of a national road that is very important as a land transportation infrastructure. This road allows community mobility from one place to another, which is very important for economic and social activities (Kurniawati et al., 2022). According to Data on the Development of Road and Bridge Information Systems, Directorate of Road and Bridge Engineering, Directorate General of Highways (March 2023), of the total length of 1359.2 km of non-toll national roads in East Java, there are still 57.56% of roads in good condition, 39.79% in moderate condition, 2.46% slightly damaged, and 0.19% severely damaged. To prevent further damage, the government through the Director General of Highways of the Ministry of Public Works and Public Housing runs a Road and Bridge Preservation program to maintain optimal road conditions (Kurniawati et al., 2022).
The
Situbondo - Ketapang - Banyuwangi Road and Bridge
Preservation Work for Fiscal Year 2023-2024 aims to optimize preservation funds
and maintain road service levels. The source of funds for this project comes from the 2023-2024 State
Budget. The executor of the work is PT Bumi Duta Persada
(KSO) PT Rajendra Pratama Jaya, based on contract
number: HK.02.03-Bb8.6/1.2/736, dated June 23, 2023, with a ceiling value of
Rp. 159,332,043,000 (Kurniawati et al., 2022). The
project includes various works such as minor rehabilitation, major
rehabilitation, periodic maintenance, and bridge replacement with an
implementation period of 450 calendar days. Changes in the location of work and
adjustments to the unit price of items in this project are outlined in the contract
addendum to ensure the work goes according to plans and specifications (Kurniawati et al., 2022).
The
demands of highway users who want comfortable and safe road conditions are a
priority in this project. Therefore, reconstruction of damaged roads such as
cracks and settlement due to excessive vehicle loads is necessary. In this
case, the government has allocated APBN funds for this preservation project,
with the appointed implementer being PT Bumi Duta Persada - PT Rajendra Pratama Jaya (KSO) (Natalia et al., 2021). To overcome
delays and changes that are not in accordance with the initial contract, consistent
and integrated performance control is needed. The Earned Value Management (EVM)
concept is the right method to control project performance, ensuring the
project can be completed on time, on quality, and at the right cost (Susanti et
al., 2019).
With this method, the project can be
thoroughly monitored and evaluated to ensure that all aspects of the work are
in accordance with the original plan. EVM will be used to research the Situbondo - Ketapang - Banyuwangi Road and Bridge
Preservation project, to determine the duration and cost required until project
completion.
RESEARCH METHOD
This research investigates the Situbondo - Ketapang - Banyuwangi Road and Bridge Preservation Project in Fiscal Year 2023/2024. The focus is on evaluating project performance using the Earned Value Management (EVM) method and analyzing cost and time estimates to measure progress and efficiency.
The research took place from the third week of February to March 2024. The initial phase included preparation, preliminary survey, and literature study. Data was collected from various sources including contractors, supervision consultants, project schedules, Cost Budget Plan (RAB), and weekly reports. EVM was used as the main framework, taking into account Planned Value (PV), Earned Value (EV), and Actual Cost (AC). Variance analysis included Cost Variance (CV) and Schedule Variance (SV), with project performance assessed through Schedule Performance Index (SPI) and Cost Performance Index (CPI).
Cost and time estimates used Estimate to Complete (ETC), Estimate at Complete (EAC), and Time Estimate (TE). Project progress or delay factors are analyzed through interviews, observations, and examination of reports. The research steps include determining the background, formulating the problem, collecting and analyzing EVM data, calculating cost and time estimates, and drawing conclusions. The research aims to provide a better understanding of project performance, assisting stakeholders in decision-making related to project management and resource allocation, with the hope of improving the efficiency and effectiveness of project implementation.
RESULT AND DISCUSSION
This study evaluates the construction performance in the Situbondo - Ketapang - Banyuwangi Road and Bridge Preservation Project Fiscal Year 2023/2024 using the Earned Value Management (EVM) method. The data analyzed includes the project schedule, Budget Plan of Cost (RAB), weekly reports, and actual costs, to calculate Planned Value (PV) or Budgeted Cost of Work Scheduled (BCWS).
Table 1 PV or BCWS
Week To |
Plan Progress (%) |
Cumulative Plan (%) |
Budget (Rp) |
PV or BCWS (Rp) |
1 |
0,0430 |
0,0430 |
�23.200.000.000 |
52.976.000,00 |
2 |
0,1005 |
0,1435 |
�23.200.000.000 |
�176.844.448,38 |
3 |
0,1325 |
0,2761 |
�23.200.000.000 |
�340.136.396,76 |
4 |
0,1194 |
0,3955 |
�23.200.000.000 |
�487.291.075,24 |
5 |
0,1194 |
0,5150 |
�23.200.000.000 |
�634.445.753,72 |
6 |
0,0757 |
0,5907 |
�23.200.000.000 |
�727.683.540,63 |
7 |
0,2605 |
0,8511 |
�23.200.000.000 |
�1.048.572.123,65 |
8 |
0,4495 |
1,3006 |
�23.200.000.000 |
�1.602.384.519,96 |
9 |
0,3223 |
1,6229 |
�23.200.000.000 |
�1.999.413.079,85 |
10 |
0,8275 |
2,4504 |
�23.200.000.000 |
52.976.000,00 |
11 |
0,9519 |
3,4023 |
�23.200.000.000 |
�176.844.448,38 |
12 |
1,3033 |
4,7056 |
�23.200.000.000 |
�340.136.396,76 |
13 |
1,3238 |
6,0294 |
�23.200.000.000 |
3.018.923.515,84 |
14 |
1,4685 |
7,4979 |
�23.200.000.000 |
�4.191.660.128,92 |
15 |
1,4706 |
8,9685 |
�23.200.000.000 |
�5.797.330.290,48 |
16 |
1,5221 |
10,4906 |
�23.200.000.000 |
�7.428.213.566,89 |
17 |
3,4536 |
13,9441 |
�23.200.000.000 |
�9.237.385.927,29 |
18 |
1,2422 |
15,1863 |
�23.200.000.000 |
�1.049.166.302,21 |
19 |
3,1825 |
18,3688 |
�23.200.000.000 |
�2.924.360.260,21 |
20 |
2,8871 |
21,2558 |
�23.200.000.000 |
�7.179.147.782,60 |
21 |
0,4730 |
21,7288 |
�23.200.000.000 |
�8.709.479.059,11 |
22 |
4,3263 |
26,0551 |
�23.200.000.000 |
�2.630.331.471,05 |
23 |
4,1623 |
30,2174 |
�23.200.000.000 |
�6.187.179.493,85 |
24 |
2,7025 |
32,9199 |
�23.200.000.000 |
�6.769.885.075,22 |
25 |
2,0128 |
34,9327 |
�23.200.000.000 |
�2.099.846.663,95 |
26 |
0,3613 |
35,2940 |
�23.200.000.000 |
�7.227.825.190,77 |
27 |
2,9107 |
38,2046 |
123.200.000.000 |
40.557.272.011,94 |
28 |
0,0003 |
38,2049 |
�23.200.000.000 |
�3.037.025.400,55 |
29 |
0,5210 |
38,7259 |
�23.200.000.000 |
�3.482.166.062,93 |
30 |
0,0496 |
38,7755 |
�23.200.000.000 |
�7.068.118.478,95 |
31 |
2,6986 |
38,2049 |
�23.200.000.000 |
�7.068.473.801,49 |
32 |
0,1508 |
38,7259 |
�23.200.000.000 |
�7.710.345.801,49 |
33 |
1,0571 |
38,7755 |
�23.200.000.000 |
�7.771.442.188,30 |
34 |
0,5262 |
41,4742 |
�23.200.000.000 |
�1.096.155.121,87 |
35 |
0,7363 |
41,6250 |
�23.200.000.000 |
�1.282.000.000,00 |
36 |
1,1399 |
42,6821 |
�23.200.000.000 |
�2.584.301.175,42 |
37 |
0,8901 |
43,2083 |
�23.200.000.000 |
�3.232.613.753,16 |
38 |
0,5924 |
43,9446 |
�23.200.000.000 |
�4.139.685.918,98 |
39 |
0,5924 |
45,0845 |
�23.200.000.000 |
�5.544.085.113,69 |
40 |
1,7628 |
45,9746 |
�23.200.000.000 |
�6.640.699.393,97 |
Source:
Processed by Researchers 2024.
The analysis shows the project progress from week to week. Starting from 0.0430% with PV of IDR52,976,000 in the first week, until it reached 45.9746% with PV of IDR56,640,699,393.97 in week 40. There was a significant increase especially in week 22 and 23, where the cumulative progress reached 30.2174% and the PV reached Rp26,187,179,493.85. The project showed stability with planned improvements, signaling effective resource allocation. This analysis provides important insights for project improvement to stay within the set budget and schedule.
Earned
Value (EV) or BCWP Calculation
This study evaluates the performance of a construction project
using the Earned Value Management (EVM) method. The focus of the analysis lies
on the comparison between the initial plan and actual results, including weekly
progress and budget utilization. The data analyzed includes weekly progress,
cost realization, and Budgeted Cost of Work Performed (BCWP) for a 40-week
period.
Table 2 EV or BCWP
Week To |
Progress |
Budget (RP) |
Ev or BCWP |
||
Realization |
Cumulative |
Realization (Rp) |
Cumulative(Rp) |
||
1 |
0,0000 |
0,0000 |
123.200.000.000, |
- |
- |
2 |
0,0498 |
0,0498 |
123.200.000.000, |
61.368.856,36 |
61.368.856,36 |
3 |
0,0493 |
0,0991 |
123.200.000.000, |
60.702.856,36 |
122.071.712,73 |
4 |
0,0393 |
0,1383 |
123.200.000.000, |
48.362.485,09 |
170.434.197,82 |
5 |
0,0300 |
0,2113 |
123.200.000.000, |
36.946.242,55 |
�207.380.440,36 |
6 |
0,1077 |
0,3190 |
123.200.000.000, |
�132.688.340,90 |
� 340.068.781,26 |
7 |
0,3439 |
0,6629 |
123.200.000.000, |
423.644.974,09 |
�763.713.755,35 |
8 |
0,3345 |
0,9974 |
123.200.000.000, |
412.152.371,42 |
1.175.866.126,77
|
9 |
0,3813 |
1,3787 |
123.200.000.000, |
�469.735.958,04 |
1.645.602.084,82
|
10 |
0,4921 |
1,8708 |
123.200.000.000, |
�606.261.792,70 |
2.251.863.877,52
|
11 |
0,6494 |
2,5202 |
123.200.000.000, |
800.012.635,47 |
3.051.876.512,99
|
12 |
0,7557 |
3,2759 |
123.200.000.000, |
931.082.030,05 |
3.982.958.543,04
|
13 |
2,2644 |
5,5403 |
123.200.000.000, |
2.789.751.466,9 |
6.772.710.010,00
|
14 |
2,4951 |
8,0355 |
123.200.000.000, |
3.073.996.623,9 |
9.846.706.633,92
|
15 |
0,5865 |
8,6220 |
123.200.000.000, |
722.612.968,67 |
10.569.319.602,5 |
16 |
1,1126 |
9,7346 |
123.200.000.000, |
1.370.781.784,6 |
11.940.101.387,2
|
17 |
5,5048 |
15,2394 |
123.200.000.000, |
6.781.863.412,7 |
18.721.964.800,0 |
18 |
0,8021 |
16,0415 |
123.200.000.000, |
988.187.200,00 |
19.710.152.000,0
|
19 |
0,2456 |
16,2871 |
123.200.000.000, |
�302.579.200,00 |
20.012.731.200,0 |
20 |
0,2982 |
16,5853 |
123.200.000.000, |
367.428.671,83 |
20.380.159.871,8 |
21 |
2,7571 |
19,3424 |
123.200.000.000, |
3.396.748.298,6 |
�3.776.908.170,5 |
22 |
4,0148 |
23,3572 |
123.200.000.000, |
4.946.213.990,1 |
28.723.122.160,6 |
23 |
3,7640 |
27,1212 |
123.200.000.000, |
4.637.233.176,0 |
33.360.355.336,7 |
24 |
2,0157 |
29,1369 |
123.200.000.000, |
2.483.317.392,9 |
35.843.672.729,6 |
25 |
2,4771 |
31,6139 |
123.200.000.000, |
3.051.731.765,3 |
38.895.404.495,0 |
26 |
3,5557 |
35,1696 |
123.200.000.000, |
4.380.617.983,9 |
43.276.022.478,9
|
27 |
3,9397 |
39,1093 |
123.200.000.000, |
4.853.650.230,1 |
48.129.672.709,1 |
28 |
0,0000 |
39,1093 |
123.200.000.000, |
������� - |
48.129.672.709,1 |
29 |
0,0000 |
39,1093 |
123.200.000.000, |
������ - |
48.129.672.709,1 |
30 |
0,5283 |
39,6376 |
123.200.000.000, |
650.913.005,13 |
48.780.585.714,2 |
31 |
0,5283 |
40,1660 |
123.200.000.000, |
650.913.005,13 |
49.431.498.719,3 |
34 |
0,1570 |
42,5057 |
123.200.000.000 |
193.445.968,56 |
52.314.055.745,8 |
35 |
0,4118 |
42,9175 |
123.200.000.000, |
507.335.390,03 |
52.821.391.135,8 |
36 |
1,2487 |
44,1662 |
123.200.000.000, |
1.538.387.337,3 |
54.359.778.473,2 |
37 |
0,6640 |
44,8302 |
123.200.000.000, |
818.031.375,21 |
55.177.809.848,4 |
38 |
0,1828 |
45,0130 |
123.200.000.000, |
225.266.490,77 |
55.403.076.339,1 |
39 |
0,2594 |
45,2724 |
123.200.000.000, |
319.569.357,97 |
55.722.645.697,1 |
40 |
2,8798 |
48,1522 |
123.200.000.000 |
3.547.926.859,5 |
59.270.572.556,7 |
Source:
Processed by Researchers 2024.
Based
on table 2 states that in the second week, the project achieved a progress of
0.0498% with BCWP IDR61,368,856.36. Until week 10, the cumulative progress
reached 1.8708% with BCWP IDR 2,251,863,877.52. A significant increase occurred
in week 17 (15.2394% cumulative progress with BCWP IDR 18,721,964,800.00) and
weeks 22 and 23 (progress of 23.3572% and 27.1212% respectively with cumulative
BCWP IDR 33,360,355,336.70). In
week 40, the project reached a cumulative progress of 48.1522% with a BCWP of
IDR59,270,572,556.70. Despite a few weeks without significant progress, the
project showed a steady increase in progress. This analysis helps monitor
resource allocation and adjust strategies to maintain project adherence to
budget and schedule targets.
This analysis assesses the 40-week project performance using the Earned Value Management (EVM) method, focusing on the comparison between Planned Value (PV), Earned Value (EV), and Actual Cost (AC).
Table 3 Comparison of PV, EV, and AC
Week to |
PV or BCWS (Rp) |
EV or BCWP (Rp) |
Actual Cost (Rp) |
1 |
52.976.000,00 |
- |
|
2 |
176.844.448,38 |
61.368.856,36 |
|
3 |
340.136.396,76 |
122.071.712,73 |
|
4 |
487.291.075,24 |
170.434.197,82 |
|
5 |
634.445.753,72 |
207.380.440,36 |
|
6 |
727.683.540,63 |
340.068.781,26 |
|
7 |
1.048.572.123,65 |
763.713.755,35 |
|
8 |
1.602.384.519,96 |
1.175.866.126,77 |
|
9 |
1.999.413.079,85 |
1.645.602.084,82 |
|
10 |
3.018.923.515,84 |
2.251.863.877,52 |
|
11 |
4.191.660.128,92 |
3.051.876.512,99 |
|
12 |
5.797.330.290,48 |
3.982.958.543,04 |
|
13 |
7.428.213.566,89 |
6.772.710.010,00 |
|
14 |
9.237.385.927,29 |
9.846.706.633,92 |
|
15 |
11.049.166.302,21 |
10.569.319.602,59 |
|
16 |
12.924.360.260,21 |
11.940.101.387,25 |
|
17 |
17.179.147.782,60 |
18.721.964.800,00 |
155.535.750,00 |
18 |
18.709.479.059,11 |
19.710.152.000,00 |
1.234.202.250,00 |
19 |
22.630.331.471,05 |
20.012.731.200,00 |
1.234.202.250,00 |
20 |
26.187.179.493,85 |
20.380.159.871,83 |
7.124.011.500,00 |
21 |
26.769.885.075,22 |
23.776.908.170,51 |
7.124.011.500,00 |
22 |
32.099.846.663,95 |
28.723.122.160,68 |
12.946.810.500,00 |
23 |
37.227.825.190,77 |
33.360.355.336,77 |
25.982.046.197,60 |
24 |
40.557.272.011,94 |
35.843.672.729,67 |
25.982.046.197,60 |
25 |
43.037.025.400,55 |
38.895.404.495,03 |
25.982.046.197,60 |
26 |
43.482.166.062,93 |
43.276.022.478,95 |
25.982.046.197,60 |
27 |
47.068.118.478,95 |
48.129.672.709,14 |
39.267.286.950,60 |
28 |
47.068.473.801,49 |
48.129.672.709,14 |
40.978.107.352,20 |
29 |
47.710.345.801,49 |
48.129.672.709,14 |
40.978.107.352,20 |
30 |
47.771.442.188,30 |
48.780.585.714,27 |
40.978.107.352,20 |
31 |
51.096.155.121,87 |
49.431.498.719,39 |
40.978.107.352,20 |
32 |
51.282.000.000,00 |
50.512.000.000,00 |
40.978.107.352,20 |
33 |
52.584.301.175,42 |
52.120.609.777,29 |
40.978.107.352,20 |
34 |
53.232.613.753,16 |
52.314.055.745,85 |
40.978.107.352,20 |
35 |
54.139.685.918,98 |
52.821.391.135,88 |
42.184.352.968,20 |
36 |
55.544.085.113,69 |
54.359.778.473,21 |
42.184.352.968,20 |
37 |
56.640.699.393,97 |
55.177.809.848,42 |
42.184.352.968,20 |
38 |
57.370.523.512,43 |
55.403.076.339,19 |
42.184.352.968,20 |
39 |
58.100.347.630,90 |
55.722.645.697,16 |
42.184.352.968,20 |
40 |
60.272.113.645,19 |
59.270.572.556,73 |
8.597.173.030,20 |
Source:
Processed by Researchers 2024.
At the start of the project, the PV
reached IDR52,976,000 and the EV started to be measurable in the second week.
During the first 10 weeks, EV consistently increased but was below the PV,
indicating steady but slow progress. A significant improvement occurred in week
17 with EV surpassing PV, indicating accelerated project implementation.
However, cost spikes occurred from week 20 onwards. By week 40, the project was
almost complete with a PV of Rp60,272,113,645.19, EV of Rp59,270,572,556.73,
and AC of Rp8,597,173,030.20. Overall, the project is on track with some
manageable cost deviations.
Calculation of Project Performance,
Cost Estimation and Project Completion Time
This analysis assesses the 40-week project performance using the Earned Value Management (EVM) method, focusing on the comparison between Planned Value (PV), Earned Value (EV), and Actual Cost (AC).
Table 4 PV or BCWS, EV or BCWP, Actual Cost,
Schedule Variance (SV) and Cost Variance (SV)
Sunday |
PV or BCWS (Rp) |
EV or BCWP(Rp) |
Actual Cost (Rp) |
Schedule
Variance (SV) |
1 |
52.976.000,00 |
- |
- |
-52.976.000,00 |
2 |
176.844.448,38 |
61.368.856,36 |
- |
-115.475.592,02 |
3 |
340.136.396,76 |
122.071.712,73 |
- |
-218.064.684,03 |
4 |
487.291.075,24 |
170.434.197,82 |
- |
-316.856.877,42 |
5 |
634.445.753,72 |
207.380.440,36 |
- |
-427.065.313,35 |
6 |
727.683.540,63 |
340.068.781,26 |
- |
-387.614.759,36 |
7 |
1.048.572.123,65 |
763.713.755,35 |
- |
-284.858.368,29 |
8 |
1.602.384.519,96 |
1.175.866.126,77 |
- |
-426.518.393,19 |
9 |
1.999.413.079,85 |
1.645.602.084,82 |
- |
-353.810.995,03 |
10 |
3.018.923.515,84 |
2.251.863.877,52 |
- |
-767.059.638,32 |
11 |
4.191.660.128,92 |
3.051.876.512,99 |
- |
-1.139.783.615,93 |
12 |
5.797.330.290,48 |
3.982.958.543,04 |
- |
-1.814.371.747,44 |
13 |
7.428.213.566,89 |
6.772.710.010,00 |
- |
-655.503.556,89 |
14 |
9.237.385.927,29 |
9.846.706.633,92 |
- |
609.320.706,63 |
15 |
11.049.166.302,21 |
10.569.319.602,59 |
- |
-479.846.699,62 |
16 |
12.924.360.260,21 |
11.940.101.387,25 |
- |
-984.258.872,96 |
17 |
17.179.147.782,60 |
18.721.964.800,00 |
155.535.750,00 |
1.542.817.017,40 |
18 |
18.709.479.059,11 |
19.710.152.000,00 |
1.234.202.250,00 |
1.000.672.940,89 |
19 |
22.630.331.471,05 |
20.012.731.200,00 |
1.234.202.250,00 |
-2.617.600.271,05 |
20 |
26.187.179.493,85 |
20.380.159.871,83 |
7.124.011.500,00 |
-5.807.019.622,02 |
21 |
26.769.885.075,22 |
23.776.908.170,51 |
7.124.011.500,00 |
-2.992.976.904,71 |
22 |
32.099.846.663,95 |
28.723.122.160,68 |
12.946.810.500,00 |
-3.376.724.503,27 |
23 |
37.227.825.190,77 |
33.360.355.336,77 |
25.982.046.197,60 |
-3.376.724.503,27 |
24 |
40.557.272.011,94 |
35.843.672.729,67 |
25.982.046.197,60 |
-3.867.469.854,01 |
25 |
43.037.025.400,55 |
38.895.404.495,03 |
25.982.046.197,60 |
-4.713.599.282,27 |
26 |
43.482.166.062,93 |
43.276.022.478,95 |
25.982.046.197,60 |
-4.141.620.905,51 |
27 |
47.068.118.478,95 |
48.129.672.709,14 |
39.267.286.950,60 |
-206.143.583,98 |
28 |
47.068.473.801,49 |
48.129.672.709,14 |
40.978.107.352,20 |
1.061.554.230,19 |
29 |
47.710.345.801,49 |
48.129.672.709,14 |
40.978.107.352,20 |
1.061.198.907,65 |
30 |
47.771.442.188,30 |
48.780.585.714,27 |
40.978.107.352,20 |
419.326.907,65 |
31 |
51.096.155.121,87 |
49.431.498.719,39 |
40.978.107.352,20 |
1.009.143.525,97 |
32 |
51.282.000.000,00 |
50.512.000.000,00 |
40.978.107.352,20 |
-1.664.656.402,47 |
33 |
52.584.301.175,42 |
52.120.609.777,29 |
40.978.107.352,20 |
-770.000.000,00 |
34 |
53.232.613.753,16 |
52.314.055.745,85 |
40.978.107.352,20 |
-918.558.007,31 |
35 |
54.139.685.918,98 |
52.821.391.135,88 |
42.184.352.968,20 |
-1.318.294.783,10 |
36 |
55.544.085.113,69 |
54.359.778.473,21 |
42.184.352.968,20 |
-1.184.306.640,47 |
37 |
56.640.699.393,97 |
55.177.809.848,42 |
42.184.352.968,20 |
-1.462.889.545,55 |
38 |
57.370.523.512,43 |
55.403.076.339,19 |
42.184.352.968,20 |
-1.967.447.173,24 |
39 |
58.100.347.630,90 |
55.722.645.697,16 |
42.184.352.968,20 |
-2.377.701.933,73 |
40 |
60.272.113.645,19 |
59.270.572.556,73 |
48.597.173.030,20 |
-1.001.541.088,46 |
Source:
Processed by Researchers 2024.
At the start of the project, progress was slow with PV reaching Rp52,976,000.00 and EV starting to be measured in the second week. During the first 10 weeks, EV increased consistently but was below the PV, indicating steady but slow progress. A significant improvement occurred in week 17 with EV surpassing PV, indicating an acceleration in project implementation. However, a spike in actual costs was seen from week 20 onwards.
At week 40, the project was nearing completion with a PV of Rp60,272,113,645.19, EV of Rp59,270,572,556.73, and AC of Rp8,597,173,030.20. Overall, the project is on track with some manageable cost deviations.
Analysis of project performance for 40 weeks using the Earned Value Management (EVM) method aims to evaluate the effectiveness of project implementation by comparing Planned Value (PV), Earned Value (EV), and Actual Cost (AC), as well as measuring Schedule Performance Index (SPI) and Cost Performance Index (CPI).
Table 5 Time Performance Index (SPI) and Cost
Performance Index (CPI)
Sunday |
PV or BCWS |
EV or BCWP |
ACWP |
SPI |
CPI |
1 |
52.976.000,00 |
- |
�
- |
0,000 |
0,000 |
2 |
176.844.448,38 |
61.368.856,36 |
�-
|
0,347 |
0,000 |
3 |
340.136.396,76 |
122.071.712,73 |
- |
0,359 |
0,000 |
4 |
487.291.075,24 |
170.434.197,82 |
- |
0,350 |
0,000 |
5 |
634.445.753,72 |
207.380.440,36 |
������
- |
0,327 |
0,000 |
6 |
�727.683.540,63 |
340.068.781,26 |
������������ - |
0,467 |
0,000 |
7 |
1.048.572.123,65 |
763.713.755,35 |
���������
- |
0,728 |
0,000 |
8 |
1.602.384.519,96 |
1.175.866.126,77 |
����������� - |
0,734 |
0,000 |
9 |
1.999.413.079,85 |
1.645.602.084,82 |
��
- |
0,823 |
0,000 |
10 |
3.018.923.515,84 |
2.251.863.877,52 |
�
- |
0,746 |
0,000 |
11 |
4.191.660.128,92 |
3.051.876.512,99 |
������
- |
0,728 |
0,000 |
12 |
5.797.330.290,48 |
3.982.958.543,04 |
������������� - |
0,687 |
0,000 |
13 |
7.428.213.566,89 |
6.772.710.010,00 |
�������
- |
0,912 |
0,000 |
14 |
9.237.385.927,29 |
9.846.706.633,92 |
���
- |
1,066 |
0,000 |
15 |
11.049.166.302,21 |
10.569.319.602,59 |
���
- |
0,957 |
0,000 |
16 |
12.924.360.260,21 |
11.940.101.387,25 |
�����
- |
0,924 |
0,000 |
17 |
17.179.147.782,60 |
18.721.964.800,00 |
155.535.750,00 |
1,090 |
##### |
18 |
18.709.479.059,11 |
19.710.152.000,00 |
1.234.202.250,00 |
1,053 |
15,970 |
19 |
22.630.331.471,05 |
20.012.731.200,00 |
1.234.202.250,00 |
0,884 |
16,215 |
20 |
26.187.179.493,85 |
20.380.159.871,83 |
7.124.011.500,00 |
0,778 |
2,861 |
21 |
26.769.885.075,22 |
23.776.908.170,51 |
7.124.011.500,00 |
0,888 |
3,338 |
22 |
32.099.846.663,95 |
28.723.122.160,68 |
12.946.810.500,00 |
0,895 |
2,219 |
23 |
37.227.825.190,77 |
33.360.355.336,77 |
25.982.046.197,60 |
0,896 |
1,284 |
24 |
40.557.272.011,94 |
35.843.672.729,67 |
25.982.046.197,60 |
0,884 |
1,380 |
25 |
43.037.025.400,55 |
38.895.404.495,03 |
25.982.046.197,60 |
0,904 |
1,497 |
26 |
43.482.166.062,93 |
43.276.022.478,95 |
25.982.046.197,60 |
0,995 |
1,666 |
27 |
47.068.118.478,95 |
48.129.672.709,14 |
39.267.286.950,60 |
1,023 |
1,226 |
28 |
47.068.473.801,49 |
48.129.672.709,14 |
40.978.107.352,20 |
1,023 |
1,175 |
29 |
47.710.345.801,49 |
48.129.672.709,14 |
40.978.107.352,20 |
1,009 |
1,175 |
30 |
47.771.442.188,30 |
48.780.585.714,27 |
40.978.107.352,20 |
1,021 |
1,190 |
31 |
51.096.155.121,87 |
49.431.498.719,39 |
40.978.107.352,20 |
0,967 |
1,206 |
32 |
51.282.000.000,00 |
50.512.000.000,00 |
40.978.107.352,20 |
0,985 |
1,233 |
33 |
52.584.301.175,42 |
52.120.609.777,29 |
40.978.107.352,20 |
0,991 |
1,272 |
34 |
53.232.613.753,16 |
52.314.055.745,85 |
40.978.107.352,20 |
0,983 |
1,277 |
35 |
54.139.685.918,98 |
52.821.391.135,88 |
42.184.352.968,20 |
0,976 |
1,252 |
36 |
55.544.085.113,69 |
54.359.778.473,21 |
42.184.352.968,20 |
0,979 |
1,289 |
37 |
56.640.699.393,97 |
55.177.809.848,42 |
42.184.352.968,20 |
0,974 |
1,308 |
38 |
57.370.523.512,43 |
55.403.076.339,19 |
42.184.352.968,20 |
0,966 |
1,313 |
39 |
58.100.347.630,90 |
55.722.645.697,16 |
42.184.352.968,20 |
0,959 |
1,321 |
40 |
60.272.113.645,19 |
59.270.572.556,73 |
48.597.173.030,20 |
0,983 |
1,220 |
The project initially
experienced significant delays, indicated by SPI below 1. However, starting
from week 13, the project showed
improvement with SPI close to 1. By week 14, the project achieved excellence with SPI above 1, signaling schedule efficiency. Despite facing cost
challenges, especially in week 20 with a drastically reduced CPI, the project
managed to maintain a CPI above 1 after week 26, indicating better cost
control. At the end of the period, the project was nearing completion with PV
of IDR60,272,113,645.19, EV of IDR59,270,572,556.73, and AC of
IDR48,597,173,030.20. SPI was at 0.983 and CPI at 1.220, indicating relative
efficiency with controlled costs, despite challenges throughout the project.
Calculation of
Estimated Project Time and Cost
The calculation of cost forecasts and project completion schedules provides an overview of the cost at the end of the project (Estimate at Completion = EAC) and the estimated project completion time (Estimate all Schedule = EAS).
1. Project Time Forecast
In week 40, the estimated remaining work time (ETS) is calculated using the formula ETS = (remaining time) / SPI. With an SPI value of 0.98338, ETS is calculated to be 178 days. Then, to calculate the estimated time to complete all work (EAS), ETS was added to the finish time, resulting in an EAS of 453 days. Thus, the project work time is estimated to be 3 days longer than the original schedule, which can be anticipated by increasing working hours.
2. Final Project Cost Forecast
In week 65, the estimated remaining
cost (ETC) is calculated using the formula ETC = (Budget - BCWP) / SPI. With an
SPI value of 0.9919, the ETC is calculated to be Rp 914,061,685. Then, the
estimated final project cost (EAC) is calculated by adding the ETC to the
actual cost (ACWP), resulting in an EAC of Rp 112,439,121,070.91. This cost is
less than the contract value of IDR 123,200,000,000, indicating potential
savings at the end of the project.
CONCLUSION
Based on the Earned Value analysis of the Situbondo - Ketapang - Banyuwangi Road and Bridge Preservation Project, it is concluded: 1. Cost performance (CPI > 1) indicates good cost management, but time performance (SPI < 1) indicates delay from planned. 2. The estimated cost through Estimate Temporary Cost is Rp 914,061,685, while the estimated final cost of the project is Rp 112,439,121,070.91. The estimated completion time is 178 days (Estimate Temporary Schedule) with an overall estimate of 453 days, 3 days longer than the original schedule.
Based on the above conclusions, there are several suggestions that can be given, among others: 1. Service providers should use the Earned Value Method from the beginning of the project to avoid cost and time mismatches. The use of the CPM method with Microsoft Project can improve scheduling. 2. The author is advised to expand the literature review and references to explore influential work and cost calculations to avoid delays.
REFERENCES
Alkas, M. J., Sari, D. P., Haryanto,
B., & Ramadanri, N. A. (2023). Pengendalian
Biaya Dan Waktu Proyek Dengan Metode Analisis Nilai
Hasil Menggunakan Microsoft Project (Vol. 1, Issue 1). Doi.
Arifin, M. F. A., Sarifatuzzuhriyah,
M., & Liu, S. S. (2023). Cost And
Time Control Analysis With Earned Value Method In The Mrt-Hub Building Construction. Jurnal
Teknik Sipil Dan Perencanaan,
25(1), 90�99. Https://Doi.Org/10.15294/Jtsp.V25i1.43043
Asmoro,
M. R., Witjaksana, B., & Tjendani,
H. T. (2023). Cost And Time Analysis Using Earned Value Method Construction Of Upbjj Building Open University
Of Surabaya Phase Ii. In Asian Journal Of Engineering, Social And Health (Vol. 2, Issue 12).
Bambang
Siswanto, A., & Afif Salim, M. (2019). Manajemen
Proyek Pengadaan Jasa Konstruksi Dengan E-Procurement
View Project International Journal Of Civil
Engineering And Technology View Project.
Https://Www.Researchgate.Net/Publication/339787455
Bonny, A., Oetomo,
W., & Marleno, R. (2022). Analysis Of Time And Cost Control
Using The Earned Value Method In Well Pad Hilling And Compacting Work In The
Pt. Pertamina Hulu Rokan Riau Province. Devotion
Journal Of Community Service, 3(14).
Https://Doi.Org/10.36418/Dev.V3i14.339
Christy,
G. M., Puspasari, V. H., & Nuswantoro, W. (2023).
Analisis Pengendalian Biaya Dan Waktu Dengan Metode
Nilai Hasil Pada Pembangunan Jalan Simpang Empat Gedung Baru Universitas Palangka
Raya. Bentang : Jurnal
Teoritis Dan Terapan Bidang Rekayasa Sipil, 11(2), 209�216.
Https://Doi.Org/10.33558/Bentang.V11i2.6944
E-Book-Manajemen-Proyek. (N.D.).
Ismail,
I., & Darkasyi, D. (2023). Pengendalian
Biaya Dan Waktu Pada Proyek
Rekonstruksijalan Pante Gurah � Tanohanoe
Kecamatan Muara Batu Dengan
Metode Earned Value. Jurnal Rekayasa Teknik Dan Teknologi,
7(1). Https://Doi.Org/10.51179/Rkt.V7i1.1827
Iyan
Pamungkas, W., & Andreas, A. (2021). Analisis Biaya Dan Waktu Proyek Dalam Proses Kinerja Dengan
Menggunakan Metode Earned Value Studi Kasus: Proyek Rancang Bangun Rumah Susun Stasiun Pondok Cina (Analysis Of
Project Costs And Time In Process Performance With Using The Earned Value
Method Design And Build Project Of Pondok Cina
Station Flats ). In Jurnal
Artesis (Vol. 1, Issue 2).
Ida
Bagus Gede Indramanik, K., Kadek Astariani,
N., & Wayan Sudiarsana, Dan I. (2022). Analisa
Kinerja Biaya Dan Waktu Menggunakan
Metode Konsep Nilai Hasil (Earned Value Concept)
Kasus, S., Pembangunan Gedung Ruang Kelas Baru
Madrasah Tsanawiyah Negeri, P., Karangasem. In Jurnal Teknik Gradien
(Vol. 14, Issue 02). Http://Www.Ojs.Unr.Ac.Id/Index.Php/Teknikgradien
M.,
Irawan, J., Rijaluddin, A., & Juliar, E. (2019). Pengendalian Konsep Nilai
Hasil Pada Proyek Pembangunan Gedung Satpol Pp Kabupaten Majalengka (Vol. 05, Issue 02).
Proboretno,
W., Witjaksana, B., & Tjendani,
H. T. (2024). Time Performance Analysis On Afv Earthwork In Kedungpeluk Sidoarjo Using The Earned Value Method. Social Sciences And Business (Jhssb) Jhssb | Volume, 3(2).
Https://Ojs.Transpublika.Com/Index.Php/Jhssb/
Riduwan,
S. P., Witjaksana, B., & Tjendani,
H. T. (2023). Cost And Time Analysis Using Earned Value Method In The Construction Of Sports Facilities In Kecamatan Kedewan Kabupaten Bojonegoro. In Asian
Journal Of Engineering, Social And Health (Vol. 2,
Issue 12). Https://Ajesh.Ph/Index.Php/Gp
Rifatul
Muniroh, M. �, Kempa, M.,
& Buyang, C. G. (2024). Pengendalian
Biaya Dan Waktu Dengan
Earned Value Concept Pada Proyek Penataan
Bangunan. Jurnal Simetrik, 11(1).
Ritonga,
R. A., Megayanti, A., & Herawati, H. (2023). Penerapan Tools Manajemen Proyek Pada Pt. Krakatau It Cilegon.
Jika (Jurnal Informatika),
7(2). Https://Doi.Org/10.31000/Jika.V7i2.7674
Slamet
Pratama, V. (2022). Analisis
Terhadap Biaya Dan Waktu Menggunakan Metode Earned Value Analysis (Eva) Pada Lokasi Proyek Kontruksi.
Sujarwo,
A., & Oetomo, W. (2022). Analisis
Waktu Dan Biaya Pembangunan Gedung Ikfm, Ips, Ipl Dan Parkir Kendaraan Karyawan. Jurnal Kacapuri : Jurnal Keilmuan Teknik Sipil, 5(1).
Https://Doi.Org/10.31602/Jk.V5i1.7527