Eduvest �
Journal of Universal Studies Volume 4
Number 9, September, 2024 p- ISSN
2775-3735- e-ISSN 2775-3727 |
||
|
|
|
ANALYSIS OF COST AND TIME USING EARNED VALUE ON THE BOARDING SCHOOL
CONSTRUCTION PROJECT AT SMA MUHAMMADIYAH 3 TULANGAN SIDOARJO |
|
|
Titik Nurkaruniati�, Budi Witjaksana�, Hanie
Teki Tjendani� 1,2,3 Universitas
17 Agustus 1945 Surabaya, Indonesia Email: [email protected],
[email protected], [email protected] |
|
|
ABSTRACT |
|
|
Effective project management is crucial for
the successful completion of construction projects, including the
construction of a dormitory at SMA Muhammadiyah 3 Tulangan. Challenges such
as design changes, adverse weather conditions, and limited labor resources
impact the project's progress. The Earned Value Method is used to monitor
project performance by analyzing indicators like BCWS, BCWP, ACWP, SV, CV,
SPI, and CPI. This analysis shows that the project initially experienced
delays and exceeded budget costs, but the situation improved significantly
over time. Despite weekly variations in costs, the project remained on a
financially manageable track. The conclusion from this analysis is that while
the project faced time delays, cost performance remained under control.
Recommendations for improvement include more thorough planning, better
resource management, and quicker responses to changes. |
|
|
KEYWORDS |
Boarding School
Construction, Project Performance Evaluation, Earned Value Method |
|
This work is licensed under a Creative Commons
Attribution-ShareAlike 4.0 International |
|
INTRODUCTION
The series of activities in
planning, scheduling, and controlling the course of a project aims to achieve
the desired goals, both in terms of time, quality, and cost (Rifatul Muniroh et al., 2021). In
the context of MBS dormitory construction, project management is very important
to ensure that construction goes according to plan and on time. However, there
is often a mismatch between the initial plan and the realization in the field,
which can result in delays and increased costs on the project. One of the
problems that often arise is scheduling planning that does not take into
account the limited labor resources, which must be carefully analyzed (Pratama S et al., 2022). To overcome scheduling with
limited resources, a systematic effort is needed to determine standards that
are in accordance with planning objectives or take into account the possibility
of deviations between implementation and project standards. This should be done
at the beginning and end of project construction, known as project control (Pratama et al., 2022).
In 2023, SMA Muhammadiyah 3 Tulangan launched the Muhammadiyah Boarding School (MBS)
program, which requires the school to provide dormitories for students.
However, the significant increase in the number of MBS students caused the
existing dormitories to be insufficient. To overcome this, it was decided to
build a new dormitory that could accommodate more students. CV. Tiga Anugerah
Utama was appointed as the provider to work on the construction of this new
dormitory. The contract for the construction of the dormitory started on
November 23, 2023 and is expected to be completed on May 26, 2024, in order to
be used at the start of the new academic year in June 2024. During the project
implementation, various obstacles affected the course of the project, one of
which was the design changes made midway without changing the contract value,
but only by making a Contract Change Order (CCO). These changes included
changes to the building structure and room additions, which had implications on
the cost and time of project implementation.
Erratic weather, especially frequent rains in Sidoarjo,
was also a factor that slowed down project progress. Workers could not work
optimally due to unfavorable weather conditions, and
material delivery was hampered due to slippery roads leading to the project
site. This led to increased costs and delays in project implementation. Another
obstacle faced was the lack of professional labor in
the field and the lack of ability to manage existing resources optimally. This
affected the efficiency and productivity of work in the field, and potentially
caused delays in project completion. The decision not to purchase new materials
for the formwork also slowed down the construction process, despite having the
potential to save costs.
Although the original contract was only to build the ground floor, the
contractor decided to continue the construction up to the third floor with a
loan from the contractor and approval from the school. This was done without
changing the timing of the project, but still ensured that the building could
be used in the new school year. In the face of these challenges, a method is
needed that can help in controlling the cost and time of the project. One of
the methods used is the Earned Value Method, which integrates cost and time to
evaluate project performance. This method allows project planners to predict
the length of time required until the project is completed and know the amount
of costs incurred until the project ends. Thus, the use of the Earned Value
Method is expected to assist in controlling the performance of the MBS
dormitory construction project of SMA Muhammadiyah 3 Tulangan,
as well as ensuring that the project can be completed on time and in accordance
with the predetermined budget.
The Earned Value method is one of
the tools used in project management that integrates cost and time. The Earned
Value method presents three dimensions, namely the physical completion of the
project (the percent complete) which reflects the planned absorption of costs
(budgeted cost), the actual costs that have been incurred or what is called
Actual Cost and what is obtained from the costs that have been incurred. It is
hoped that by using the Earned Value Method, researchers will predict the
length of time needed until the project ends in accordance with the contract
period and know the amount of costs incurred until the project ends.� From the background
above, the following problem formulation can be made:
RESEARCH METHOD
The research method for the Muhammadiyah Boarding School Construction project at SMA Muhammadiyah 3 Tulangan is a structured process that aims to analyze project performance and accurately estimate the cost and time to complete the project. This process involves steps such as determining the project background, literature review to deepen understanding, data collection through Time Schedule, Cost Budget Plan (RAB), weekly progress reports, and actual costs. These data become the basis for analyzing project performance by calculating indicators such as BCWS (Budgeted Cost of Work Scheduled), BJWP (Budgeted Cost of Work Performed), ACWP (Actual Cost of Work Performed), CV (Cost Variance), SV (Schedule Variance), CPI (Cost Performance Index), and SPI (Schedule Performance Index). Calculation of cost estimates and project completion times using predetermined formulas based on the data that has been collected.
These estimates are important to provide an accurate picture of the resource requirements and expected project schedule. Afterwards, the researcher summarizes the project performance and provides cost and time estimates for project completion as a basis for stakeholders. The method was carefully designed to ensure proper data collection and in-depth analysis to provide a comprehensive understanding of the project performance. This method ensures that the MBS dormitory construction project of SMA Muhammadiyah 3 Tulangan can be run efficiently and in accordance with the established plan.
There are several
stages in analyzing project performance, the first is determining the values of
planed value, earned value, actual cost, schedule variance, cost variance,
schedule performance index, cost performance index, estimate to complete,
estimate at complete, and time estimated.
-
BCWS (Bugeted
Cost of Work Scheduled) is the amount of budgeted costs for work scheduled for
a certain period of time and which is specified in the budget, obtained by
multiplying the percentage of progress plans contained in the time schedule
with the project implementation costs listed in the RAB. The BCWS value is
calculated using equation 2.3.
-
BCWP (budgeted cost of work performed) is
the amount of costs incurred, for work that has been carried out, obtained by
multiplying the percentage of progress that has been carried out by the budget
BCWP value is calculated using equation 2.2.
-
ACWP (Actual Cost Of
Work Performed) is the actual cost expenditure, of the work that has been done
up to a certain period of time. These costs are obtained from accounting data
on the reporting date, records of all direct costs, non-overhead costs and
other costs. This calculation is only an estimate or estimate that is assumed
to be the real cost used. ACWP = (Weight of implementation per week / Weight of
overall plan) x Total Budget Cost The BCWS value is
calculated using equation 2.1.
-
CV (Cost Variance) / Cost variance, the
difference between the cost provided for the work that has been done (BCWP) and
the actual cost of the work that has been carried out (ACWP) and the integrated
schedule, it has been mentioned earlier that analyzing project progress with
simple variance analysis is considered insufficient, because this method does
not integrate aspects of cost and schedule. To overcome this, BCWS, BCWP, and
ACWP indicators are used in determining Cost Variance and Schedule Variance in an
integrated manner. Cost Variance (CV) and Schedule Variance (SSV) are
calculated by equation 2.4.
-
CPI (Cost Performed Index)/ Cost
Productivity and Performance Index, a comparison between the budgeted cost of
the work activities performed (BCWP) and the actual cost of the work activities
performed (ACWP). Project managers often want to know the efficiency of
resource use, which can be expressed as a productivity index or performance
index. This performance index consists of the Cost Performance Index (CPI) and
Schedule Performance Index (SPI). CPI is calculated by equation 2.6 and SPI is
calculated by equation 2.7.
-
Projected Cost Expenditure and Project
Completion Timeframe, making a cost forecast or project completion schedule
based on the indicators obtained at the time of reporting, will provide an
indication of the amount of cost at the end of the project (Estimate At Completion = EAC) calculated by equation 2.10 and the
estimated project completion time (Estimate All Schedule = EAS) calculated by
equation 2.12. Cost or schedule forecasts are very useful because they provide
an early warning of things that will happen in the future, if the trends that
exist at the time of reporting do not change. If the remaining work is considered to be performing
as it was at the time of reporting,
-
�After obtaining the calculation of the amount
of cost at the end of the project (Estimate At Completion = EAC) calculated by
equation 2.10 and the estimated project completion time (Estimate Time Schedule
= ETS) calculated by equation 2.11, the calculation continues by calculating
the amount of cost needed to complete the project without any additional time
assuming that the estimated project completion time (Estimate All Schedule =
EAS) is the same as the Implementation Time Plan (T total) calculated using
formula 2.12.
RESULT AND DISCUSSION
In monitoring the progress of the Muhammadiyah Boarding School Dormitory Construction project at SMA Muhammadiyah 3 Tulangan, we use important indicators such as BCWS, BCWP, and ACWP. The weekly data in Table 1 provides an overview of the planning and cost realization during the first 15 weeks of project implementation. From this data, we can evaluate the project's adherence to the cost plan and understand the cost realization of the project.
Table 1 Recapitulation of BCWS, BCWP, and ACWP calculation results
Week To |
BCWS |
BCWP |
ACWP |
1 |
�4.484.442,31 |
3.000.000,00
|
�246.080.500,00 |
2 |
� 75.804.683,86 |
�8.753.500,00 |
251.280.500,00 |
3 |
� 174.349.730,08 |
�64.032.401,31 |
�336.130.600,00 |
4 |
�272.894.776,30 |
�133.470.044,19 |
�359.524.000,00 |
5 |
371.439.822,52 |
�298.420.282,61 |
�397.366.068,00 |
6 |
457.735.391,43 |
�477.083.229,15 |
430.143.568,00 |
7 |
�586.159.877,02 |
�626.295.393,18 |
464.850.218,00 |
8 |
�769.244.924,76 |
�865.650.315,09 |
489.217.218,00 |
9 |
1.033.135.158,57 |
�1.055.757.015,95 |
594.681.718,00 |
10 |
1.299.107.250,20 |
�1.227.673.105,24 |
650.083.718,00 |
11 |
1.502.795.964,89 |
�1.396.394.111,75 |
667.422.118,00 |
12 |
1.685.502.190,22 |
�1.580.565.545,74 |
691.585.018,00 |
13 |
1.868.208.415,55 |
�1.951.272.869,19 |
869.537.474,00 |
14 |
2.050.914.640,87 |
�2.021.090.443,09 |
�
963.930.274,00 |
15 |
2.396.739.592,51 |
�2.204.079.461,19 |
997.423.774,00 |
Source: Processed by Researchers, 2024
The data in Table 1 shows an improvement in the project's cost performance and efficiency after the initial few weeks that showed high actual costs compared to the planned budget. Although some challenges remained until the last week analyzed, the project gradually showed improvements in cost management and job efficiency.
Calculation
of Schedule Variance (SV) and Cost Variance (CV) Values
To monitor the progress of the Muhammadiyah Boarding School Dormitory Construction project at SMA Muhammadiyah 3 Tulangan, we calculate Schedule Variance (SV) and Cost Variance (CV). SV measures schedule variances, while CV shows cost variances. Table 2 displays the weekly values of SV and CV, where negative values indicate delays and cost overruns, while positive values indicate the project is running on or ahead of schedule with costs under budget.
Table 2 Schedule Variance (SV) Value and Cost Variance (CV) Value
Week To |
SV |
Description |
CV |
Description |
1 |
-1.484.442,31 |
Negative |
-243.080.500,00 |
Negative |
2 |
-67.051.183,86 |
Negative |
-242.527.000,00 |
Negative |
3 |
-110.317.328,77 |
Negative |
-272.098.198,69 |
Negative |
4 |
-139.424.732,11 |
Negative |
-226.053.955,81 |
Negative |
5 |
-73.019.539,92 |
Negative |
-98.945.785,39 |
Negative |
6 |
19.347.837,70 |
Positive |
46.939.661,15 |
Positive |
7 |
40.135.516,14 |
Positive |
161.445.175,18 |
Positive |
8 |
96.405.390,31 |
Positive |
376.433.097,09 |
Positive |
9 |
22.621.857,36 |
Positive |
461.075.297,95 |
Positive |
10 |
-71.434.145,00 |
Negative |
577.589.387,24 |
Positive |
11 |
-106.401.853,17 |
Negative |
728.971.993,75 |
Positive |
12 |
-104.936.644,52 |
Negative |
888.980.527,74 |
Positive |
13 |
83.064.453,60 |
Positive |
1.081.735.395,19 |
Positive |
14 |
-29.824.197,83 |
Negative |
1.057.160.169,09 |
Positive |
15 |
-192.660.131,37 |
Negative |
1.206.655.687,19 |
Positive |
Source: Processed by researchers, 2024.
In
table 2 it is found that weeks 1-5, the project is
delayed and costs are over budget (negative SV and CV). In weeks 6-9, the
project was on schedule and costs were under budget (SV and CV positive). Weeks 10-12 showed delays but costs
were under control (negative SV, positive CV). Week 13, the project was back on
schedule and cost (SV and CV positive). However, in weeks 14-15, the project
again experienced delays although costs remained under control (negative SV,
positive CV).
Calculation
of Schedule Performance Index (SPI) and Cost Performance Index (CPI)
To monitor the progress of the Muhammadiyah Boarding School Dormitory Construction project at SMA Muhammadiyah 3 Tulangan, we calculated the Schedule Performance Index (SPI) and Cost Performance Index (CPI). SPI measures time efficiency by comparing planned work to that completed, while CPI measures cost efficiency by comparing budgeted costs to those incurred. Table 3 displays the weekly SPI and CPI values. SPI and CPI values less than 1 indicate low time and cost efficiency, while values greater than 1 indicate high efficiency.
Table 3 Schedule Performance Index (SPI) and Cost Performance Index
(CPI)
Week To |
SPI |
Description |
CPI |
Description |
1 |
0,6690 |
Not on Target |
0,0122 |
Poor Cost
Performance |
2 |
0,1155 |
Not on Target |
0,0348 |
Poor Cost
Performance |
3 |
0,3673 |
Not on Target |
0,1905 |
Poor Cost
Performance |
4 |
0,4891 |
Not on Target |
0,3712 |
Poor Cost
Performance |
5 |
0,8034 |
Not on Target |
0,7510 |
Poor Cost
Performance |
6 |
1,0423 |
On Target |
1,1091 |
Good Cost Performance |
7 |
1,0685 |
On Target |
1,3473 |
Good Cost
Performance |
8 |
1,1253 |
On Target |
1,7695 |
Good Cost
Performance |
9 |
1,0219 |
On Target |
1,7753 |
Good Cost
Performance |
10 |
0,9450 |
Not on Target |
1,8885 |
Good Cost
Performance |
11 |
0,9292 |
Not on Target |
2,0922 |
Good Cost
Performance |
12 |
0,9377 |
Not on Target |
2,2854 |
Good Cost
Performance |
13 |
1,0445 |
On Target |
2,2440 |
Good Cost
Performance |
14 |
0,9855 |
Not on Target |
2,0967 |
Good Cost
Performance |
15 |
0,9196 |
Not on Target |
2,2098 |
Good Cost
Performance |
Source: Processed by researchers, 2024.
The SPI and CPI data showed that the project experienced initial challenges in achieving targets, particularly in terms of time delays and poor cost performance. However, over time, project performance began to improve, with better target achievement and cost performance. Although there were some periods with time performance challenges, cost performance was well maintained throughout the project.
Calculation
of Estimate to Sechedule (ETS), Estimate At Sechedule (EAS) and Remaining
Cost Estimate To Complete (ETC)
The
performance evaluation of the Muhammadiyah Boarding School Dormitory
Construction project at SMA Muhammadiyah 3 Tulangan
requires regular analysis of the Cost Budget Plan (RAB), Earned Value (BCWP),
Cost Performance Index (CPI), and estimated remaining cost (ETC). The table contains weekly data
related to RAB, BCWP, CPI, and ETC during the project period.
Table 4 Value of Estimate to Sechedule
(ETS), Estimate At Sechedule
(EAS) and Remaining Cost Estimate To Complete (ETC)
Sunday |
RAB |
BCWP |
CPI |
ETC |
1 |
2 |
3 |
3
= 1 -2� (<50%) 4= (1-2)/3� (>50%) |
|
1 |
5.617.188.890,13 |
3.000.000,00 |
0,0122 |
�5.614.188.890,13 |
2 |
5.617.188.890,13 |
�8.753.500,00 |
0,0348 |
�5.608.435.390,13 |
3 |
5.617.188.890,13 |
�64.032.401,31 |
0,1905 |
5.553.156.488,82 |
4 |
5.617.188.890,13 |
�133.470.044,19 |
0,3712 |
5.483.718.845,94 |
5 |
5.617.188.890,13 |
�298.420.282,61 |
0,7510 |
5.318.768.607,52 |
6 |
5.617.188.890,13 |
�477.083.229,15 |
1,1091 |
5.140.105.660,98 |
7 |
5.617.188.890,13 |
�626.295.393,18 |
1,3473 |
�4.990.893.496,95 |
8 |
5.617.188.890,13 |
�865.650.315,09 |
1,7695 |
4.751.538.575,04 |
9 |
5.617.188.890,13 |
1.055.757.015,95 |
1,7753 |
4.561.431.874,18 |
10 |
5.617.188.890,13 |
1.227.673.105,24 |
1,8885 |
4.389.515.784,89 |
11 |
5.617.188.890,13 |
1.396.394.111,75 |
2,0922 |
4.220.794.778,38 |
12 |
5.617.188.890,13 |
1.580.565.545,74 |
2,2854 |
4.036.623.344,39 |
13 |
5.617.188.890,13 |
1.951.272.869,19 |
2,2440 |
3.665.916.020,94 |
14 |
5.617.188.890,13 |
2.021.090.443,09 |
2,0967 |
3.596.098.447,04 |
15 |
5.617.188.890,13 |
2.204.079.461,19 |
2,2098 |
�
3.413.109.428,94 |
Source: Processed by researchers, 2024.
The project underwent significant changes from start to finish. Initially, low performance was evident from low CPI values and high estimated residual costs. However, over time, performance improved consistently, characterized by increased CPI values and decreased residual cost estimates. This indicates improved project cost management over time, resulting in more efficient performance in budget management.
Calculation
of Total Final remaining cost Estimate At Complete
(EAC)
In the Muhammadiyah Boarding School Dormitory Construction project of SMA Muhammadiyah 3 Tulangan, it is important to monitor actual expenditure (ACWP), estimated residual cost (ETC), and estimated cost at the end of the project (EAC) to evaluate performance and cost projections. Weekly data related to ACWP, ETC, and EAC have been presented in the following table.
Table 5 EAC (Estimate at Complete) Value
Sunday |
ACWP |
ETC |
EAC |
1 |
2 |
3=
1 +2 |
|
1 |
�246.080.500,00 |
5.614.188.890,13
|
5.860.269.390,13
|
2 |
251.280.500,00 |
5.608.435.390,13
|
5.859.715.890,13
|
3 |
�336.130.600,00 |
5.553.156.488,82
|
5.889.287.088,82
|
4 |
�359.524.000,00 |
5.483.718.845,94
|
�5.843.242.845,94 |
5 |
�397.366.068,00 |
5.318.768.607,52
|
5.716.134.675,52
|
6 |
430.143.568,00 |
5.140.105.660,98
|
5.570.249.228,98
|
7 |
464.850.218,00 |
4.990.893.496,95
|
5.455.743.714,95
|
8 |
489.217.218,00 |
4.751.538.575,04
|
5.240.755.793,04
|
9 |
594.681.718,00 |
4.561.431.874,18
|
5.156.113.592,18
|
10 |
650.083.718,00 |
4.389.515.784,89
|
�5.039.599.502,89 |
11 |
667.422.118,00 |
4.220.794.778,38
|
4.888.216.896,38
|
12 |
691.585.018,00 |
4.036.623.344,39
|
4.728.208.362,39
|
13 |
869.537.474,00 |
3.665.916.020,94
|
4.535.453.494,94
|
14 |
963.930.274,00 |
3.596.098.447,04
|
4.560.028.721,04
|
15 |
997.423.774,00 |
3.413.109.428,94
|
4.410.533.202,94
|
Source: Processed by researchers, 2024.
It can be seen that the project experienced significant cost variations over time. Initially, the estimated residual cost (ETC) and estimated cost at the end of the project (EAC) tended to increase, signaling a possible shift to higher-than-expected project costs. However, over time, there was a significant decrease in ETC and EAC, indicating better cost control and efficiency in project expenditure. Despite significant weekly cost variations, the project remained on a financially manageable path and made it possible to achieve the cost target at the end of the project.
CONCLUSION
Based on the Earned Value analysis that has been calculated in Chapter 4, the conclusions that can be drawn are: 1. The time performance showed project delays, with a negative Schedule Variance (-) and a Schedule Performance Index (SPI) below 1. The estimated total project execution time was 187 days, longer than the original plan of 180 days. 2. Cost performance shows a positive (+) result with a Cost Variance of Rp. 1,206,655,687. This indicates that the project cost in week 15 is lower than the budget, with a Cost Performance Index (CPI) of more than 1. The estimated total cost of project implementation is Rp. 4,367,677,048.32.
Based on the above conclusions,
there are several suggestions that can be given, among others: 1. Further
analysis needs to be carried out regarding project delays and acceleration. by
using the Precedence Diagramming Method (PDM) method to find out the
forward and backward calculations for calculating the length of project work
time. 2. Further analysis of the structure and quality of work is needed so
that the building survives as planned.
REFERENCES
Alkas, M. J., Sari, D. P., Haryanto,
B., & Ramadanri, N. A. (2023). Pengendalian
Biaya dan Waktu Proyek dengan Metode Analisis Nilai
Hasil Menggunakan Microsoft Project (Vol. 1, Issue 1). DOI.
Arifin, M. F. A., Sarifatuzzuhriyah,
M., & Liu, S. S. (2023). Cost and
Time Control Analysis with Earned Value Method in the MRT-Hub Building
Construction. Jurnal Teknik Sipil Dan Perencanaan, 25(1),
90�99. https://doi.org/10.15294/jtsp.v25i1.43043
Asmoro,
M. R., Witjaksana, B., & Tjendani,
H. T. (2023). Cost And Time Analysis Using Earned Value Method Construction Of UPBJJ Building Open University Of Surabaya Phase II. In Asian
Journal of Engineering, Social and Health (Vol. 2, Issue 12).
Bambang
Siswanto, A., & Afif Salim, M. (2019). Manajemen
Proyek Pengadaan Jasa Konstruksi Dengan E-Procurement
View project International Journal of Civil Engineering and Technology View
project. https://www.researchgate.net/publication/339787455
Bonny, A., Oetomo, W., &
Marleno, R. (2022). Analysis of Time and Cost Control
Using The Earned Value Method In Well Pad Hilling and
Compacting Work In The PT. Pertamina Hulu Rokan Riau
Province. Devotion Journal of Community Service, 3(14).
https://doi.org/10.36418/dev.v3i14.339
Christy,
G. M., Puspasari, V. H., & Nuswantoro, W. (2023).
Analisis Pengendalian Biaya dan Waktu Dengan Metode
Nilai Hasil Pada Pembangunan Jalan Simpang Empat Gedung Baru Universitas Palangka
Raya. Bentang : Jurnal
Teoritis Dan Terapan Bidang Rekayasa Sipil, 11(2), 209�216.
https://doi.org/10.33558/bentang.v11i2.6944
e-book-manajemen-proyek. (n.d.).
Ismail,
I., & Darkasyi, D. (2023). Pengendalian
Biaya Dan Waktu Pada Proyek
Rekonstruksijalan Pante Gurah � Tanohanoe
Kecamatan Muara Batu Dengan
Metode Earned Value. Jurnal Rekayasa Teknik Dan Teknologi, 7(1).
https://doi.org/10.51179/rkt.v7i1.1827
Iyan
Pamungkas, W., & Andreas, A. (2021). Analisis Biaya Dan Waktu Proyek Dalam Proses Kinerja Dengan
Menggunakan Metode Earned Value Studi Kasus: Proyek Rancang Bangun Rumah Susun Stasiun Pondok Cina (Analysis of
Project Costs and Time In Process Performance With Using the Earned Value
Method Design and Build Project of Pondok Cina
Station Flats ). In Jurnal
Artesis (Vol. 1, Issue 2).
Ida
Bagus Gede Indramanik, K., Kadek Astariani,
N., & Wayan Sudiarsana, dan I. (2022). Analisa
Kinerja Biaya Dan Waktu Menggunakan
Metode Konsep Nilai Hasil (Earned Value Concept)
Kasus, S., Pembangunan Gedung Ruang Kelas Baru
Madrasah Tsanawiyah Negeri, P., Karangasem. In Jurnal Teknik Gradien
(Vol. 14, Issue 02). http://www.ojs.unr.ac.id/index.php/teknikgradien
M.,
Irawan, J., Rijaluddin, A., & Juliar, E. (2019). Pengendalian Konsep nilai hasil pada proyek pembangunan gedung satpol pp kabupaten majalengka (Vol.
05, Issue 02).
Proboretno,
W., Witjaksana, B., & Tjendani,
H. T. (2024). Time performance analysis on afv
earthwork in kedungpeluk sidoarjo
using the earned value method. Social sciences and business (jhssb) jhssb | volume, 3(2).
https://ojs.transpublika.com/index.php/JHSSB/
Riduwan,
S. P., Witjaksana, B., & Tjendani,
H. T. (2023). Cost and time analysis using earned value method in the
construction of sports facilities in kecamatan kedewan kabupaten bojonegoro. In Asian Journal of Engineering, Social and
Health (Vol. 2, Issue 12). https://ajesh.ph/index.php/gp
Rifatul
Muniroh, M., Kempa, M., & Buyang,
C. G. (2024). PENGENDALIAN BIAYA DAN WAKTU DENGAN EARNED VALUE CONCEPT PADA
PROYEK PENATAAN BANGUNAN. JURNAL SIMETRIK, 11(1).
Ritonga,
R. A., Megayanti, A., & Herawati, H. (2023). Penerapan tools manajemen proyek pada pt. Krakatau it cilegon.
Jika (Jurnal Informatika), 7(2).
https://doi.org/10.31000/jika.v7i2.7674
Slamet Pratama, V. (2022). Analisis Terhadap Biaya
Dan Waktu Menggunakan Metode Earned Value Analysis
(Eva) Pada Lokasi Proyek Kontruksi.
Sujarwo,
A., & Oetomo, W. (2022). Analisis
Waktu dan Biaya Pembangunan Gedung IKFM, IPS, IPL Dan
Parkir Kendaraan Karyawan. Jurnal Kacapuri : Jurnal Keilmuan
Teknik Sipil, 5(1).
https://doi.org/10.31602/jk.v5i1.7527